Paragraph 39 Capital dredging, disposal conditions and debrisI1
England and Wales
If due to stress of weather or any other cause the master of a vessel determines that it is necessary to deposit the dredged material other than in accordance with the capital dredge and disposal strategy agreed under condition 34 because the safety of human life or of the vessel is threatened—
(a)
full details of the circumstances of the deposit must be notified to the MMO within 48 hours; and
(b)
at the reasonable request of the MMO the unauthorised deposits must be removed at the undertaker’s expense.