Paragraph 13 Further provisions about worksI1
England and Wales
(1)
There must be no lifting over any exposed sections of the cats pipeline or live or vulnerable plant containing hazardous substances or pressure energy.
(2)
Any construction works above the buried sections of the cats pipeline require the protection of the cats pipeline.
(3)
All piling within 1.5 metres of the centreline of a pipeline must be non-percussive, except that in the case of the cats pipeline all piling within 10 metres of the centreline of the cats pipeline must be non-percussive.
Annotations
Commencement
- I1
Sch. 9 para. 13 in force at 10.8.2016, see art. 1