OpenLegislation

Paragraph I1

England, Wales and Scotland

With Work Nos. 4a and 4b including—

(i)

construction of new highway with associated embankments, ground improvements, drainage facilities and roadside furniture;

(ii)

the provision of a hardened central reserve with a rigid concrete barrier or steel step barrier dividing the southbound and northbound carriageways;

(iii)

installation of lighting columns in the verge;

(iv)

the construction of advanced directional gantry signs, including sign foundations and sign structures;

(v)

demolition of existing verge mounted road signs and installation of replacement new road signs including sign foundations, sign structure, signs, signals, sign illumination, control cabinets, power and communication cable connections;

(vi)

treatment of underground historical mine workings to reduce the risk of ground instability to include drilling and grouting and/or installation of other protection measures;

(vii)

landscaping;

(viii)

relocation of existing internally illuminated tactical variable message sign within verge with associated ducting and reinstallation of existing CCTV in its current position; and

(ix)

associated utility works and diversions within the highway verge of each carriageway;

Annotations

Commencement

I1

Sch. 1 in force at 9.2.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble inserted (1.5.2021) by The A1 Birtley to Coal House Development Consent (Correction) Order 2021 (S.I. 2021/551), art. 1, Sch.

F2

Words in Preamble omitted (1.5.2021) by virtue of The A1 Birtley to Coal House Development Consent (Correction) Order 2021 (S.I. 2021/551), art. 1, Sch.