Paragraph 141 As-built plansI1

England and Wales

As soon as reasonably practicable following the completion of the construction of any specified works within the Port or any protective works, the undertaker must provide to PoTLL as-built plans of those works in a form and scale to be agreed between the undertaker and PoTLL.

Annotations

Commencement

I1