Paragraph 17 Traffic Monitoring and MitigationI1

England and Wales

(1)

No part of the authorised development is to commence until written details of a traffic impact monitoring and mitigation scheme has been submitted to and approved in writing by the highway authority.

(2)

The traffic impact monitoring and mitigation scheme must include—

(i)

a before and after survey to assess the changes in traffic;

(ii)

the locations to be monitored and the methodology to be used to collect the required data;

(iii)

the periods over which traffic is to be monitored;

(iv)

the method of assessment of traffic data;

(v)

control sites to monitor background growth;

(vi)

the implementation of monitoring no less than 3 months before the implementation of traffic management on the existing A14;

(vii)

agreement of baseline traffic levels;

(viii)

the submission of survey data and interpretative report to the highway authority; and

(ix)

a mechanism for the future agreement of mitigation measures.

(3)

The scheme approved under sub-paragraph (1) must be implemented by the undertaker.