OpenLegislation

Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)Plot Reference Number shown on the Land Plans(2)Purpose for which temporary possession may be taken(3)Relevant part of the authorised development
Land Plans – Sheet 1
1/2c, 1/3b, 1/8Required for construction of an attenuation pond and pipe outfall.Work No. 10
1/2dRequired to provide a new private means of access.Work No. 11
1/5a, 1/6a, 1/7c, 1/7g, 1/9b, 1/9cRequired to provide an area for construction material storage, construction access and storage of plant.All Works
1/5b, 1/6b, 1/7b, 1/7f, 1/9dRequired for the diversion of electric cables and associated auxiliary cables; required to provide an area for construction material storage, construction access and storage of plant.All Works
1/7dRequired to provide an improved private means of access.Work No. 12
Land Plans – Sheet 2
2/1a, 2/1cRequired to provide an improved private means of access.Work No. 12
2/1b, 2/2b, 2/2d, 2/2e, 2/2l, 2/4b, 2/4dRequired to provide an area for construction material storage, construction access and storage of plant.All Works
2/2a, 2/2kRequired for the diversion of electric cables and associated auxiliary cables.Work No. 9
2/1d, 2/2c, 2/2h, 2/4cRequired for the diversion of electric cables and associated auxiliary cables; required to provide an area for construction material storage, construction access and storage of plant.All Works
2/2fRequired for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials, and the treatment of site generated waste.All Works
2/2j, 2/5g, 2/9eRequired for the stopping up of the B28 Bridleway and the demolition of the bridleway bridge.Work No. 27
2/3i, 2/3k, 2/7a, 2/9dRequired for site access.All Works
2/4f, 2/4g, 2/5a, 2/5cRequired to construct a new private means of access.Work No. 11
2/6b, 2/6eRequired to provide a working area during the construction of a perimeter security fence.Work No. 16
2/6cRequired for the diversion of electric cables and associated auxiliary cables, for construction of a perimeter security fence, and for the diversion of a water pipeline.

Work No. 9

Work No. 16

Work No. 24

2/6fRequired to provide a construction working area.Work No. 17
2/9bRequired for environmental mitigation works and a construction working area.

Work No. 23

Work No. 18

2/9cRequired for the diversion of a telecommunications cable and for the diversion of a gas pipeline.

Work No. 25

Work No. 26

Land Plans – Sheet 3
3/2bRequired to provide an area for construction material storage, construction access and storage of plant.All Works