Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
| (1)Plot Reference Number shown on the Land Plans | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development |
|---|---|---|
| Land Plans – Sheet 1 | ||
| 1/2c, 1/3b, 1/8 | Required for construction of an attenuation pond and pipe outfall. | Work No. 10 |
| 1/2d | Required to provide a new private means of access. | Work No. 11 |
| 1/5a, 1/6a, 1/7c, 1/7g, 1/9b, 1/9c | Required to provide an area for construction material storage, construction access and storage of plant. | All Works |
| 1/5b, 1/6b, 1/7b, 1/7f, 1/9d | Required for the diversion of electric cables and associated auxiliary cables; required to provide an area for construction material storage, construction access and storage of plant. | All Works |
| 1/7d | Required to provide an improved private means of access. | Work No. 12 |
| Land Plans – Sheet 2 | ||
| 2/1a, 2/1c | Required to provide an improved private means of access. | Work No. 12 |
| 2/1b, 2/2b, 2/2d, 2/2e, 2/2l, 2/4b, 2/4d | Required to provide an area for construction material storage, construction access and storage of plant. | All Works |
| 2/2a, 2/2k | Required for the diversion of electric cables and associated auxiliary cables. | Work No. 9 |
| 2/1d, 2/2c, 2/2h, 2/4c | Required for the diversion of electric cables and associated auxiliary cables; required to provide an area for construction material storage, construction access and storage of plant. | All Works |
| 2/2f | Required for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials, and the treatment of site generated waste. | All Works |
| 2/2j, 2/5g, 2/9e | Required for the stopping up of the B28 Bridleway and the demolition of the bridleway bridge. | Work No. 27 |
| 2/3i, 2/3k, 2/7a, 2/9d | Required for site access. | All Works |
| 2/4f, 2/4g, 2/5a, 2/5c | Required to construct a new private means of access. | Work No. 11 |
| 2/6b, 2/6e | Required to provide a working area during the construction of a perimeter security fence. | Work No. 16 |
| 2/6c | Required for the diversion of electric cables and associated auxiliary cables, for construction of a perimeter security fence, and for the diversion of a water pipeline. | Work No. 9 Work No. 16 Work No. 24 |
| 2/6f | Required to provide a construction working area. | Work No. 17 |
| 2/9b | Required for environmental mitigation works and a construction working area. | Work No. 23 Work No. 18 |
| 2/9c | Required for the diversion of a telecommunications cable and for the diversion of a gas pipeline. | Work No. 25 Work No. 26 |
| Land Plans – Sheet 3 | ||
| 3/2b | Required to provide an area for construction material storage, construction access and storage of plant. | All Works |