Schedule 10 DOCUMENTS TO BE CERTIFIEDI1
England and Wales
| (1) Document | (2) Reference number |
|---|---|
| the book of reference | TR010044/APP/4.3 revision 4 |
| the classification of road plans | TR010044/APP/2.9 |
| the Crown land plans | TR010044/APP/2.11 revision 3 |
| the de-trunking plans | TR010044/APP/2.5 |
| the First Iteration EMP | TR010044/APP/6.8 revision 4 |
| the engineering section drawings | TR010044/APP/2.10 |
| the environmental masterplan | Figure 2.4 within TR010044/APP/6.2 revision 4 |
| the environmental statement | TR010044/APP/6.1-6.3 |
| the general arrangement plans | TR010044/APP/2.4 |
| the land plans | TR010044/APP/2.2 revision 2 |
| the streets, rights of way and access plans | TR010044/APP/2.6 revision 5 |
| the traffic regulation measures plans | TR010044/APP/2.7 |
| the permanent speed limit plans | TR010044/APP/2.8 |
| the works plans | TR010044/APP/2.3 |
| the outline construction traffic management plan | TR010044/APP/7.4 revision 5 |
| the archaeological mitigation strategy | TR010044/EXAM/9.23 revision 3 |
| the habitats plan | Figure 1 of Appendix 8.3 within TR010044/APP/6.3 |
| the biodiversity pre-commencement plan | TR010044/APP/6.13 revision 2 |
| the pre-commencement plan | TR010044/EXAM/9.48 revision 4 |
| the tree constraints plan | Appendix 7.5 Part 2 and Part 3 within TR010044/APP/6.3 revision 2 |
| scheme design approach and design principles | TR010044/EXAM/9.26 revision 3 |
| flood risk assessment | Appendix 13.4 – Flood Risk Assessment, Appendix 13.4 – Flood Risk Assessment – Annex A – River Great Ouse Hydraulic Modelling Report, Appendix 13.4 – Flood Risk Assessment – Annex B – Ordinary Watercourse Modelling Report, Appendix 13.4 – Flood Risk Assessment – Annex C – Ordinary Watercourse Hydrology Report, within TR010044/APP/6.3, and Flood Risk Assessment Technical Note TR010044/EXAM/9.82 revision 2 |
| Brook Cottages heritage strategy | TR010044/EXAM/9.104 |
Annotations
Commencement
- I1