Paragraph 22 Construction phase local traffic monitoringI1

England and Wales

(1)

No part of the authorised development is to commence until a construction phase local traffic monitoring scheme for the locations identified in the outline construction traffic management plan has been submitted to, and, following consultation with the relevant local highway authority, approved by the Secretary of State.

(2)

The construction phase local traffic management scheme must include—

(a)

a survey to assess baseline traffic at the locations identified in the outline construction traffic management plan;

(b)

the methodology to be used to collect the required data;

(c)

the periods over which construction phase traffic is to be monitored;

(d)

proposals for the submission of the survey data collected and an interpretative report to be provided to the relevant local highway authority; and

(e)

surveys as agreed in paragraphs (b) to (d) at the location in paragraph (a).

(3)

The scheme approved under sub-paragraph (1) must be implemented by the undertaker unless otherwise agreed in writing with the Secretary of State following consultation with the relevant local highway authority.