Paragraph 23 Operation phase local traffic monitoringI1
England and Wales
No part of the authorised development is to commence until an operation phase local traffic monitoring scheme has been submitted to, and following consultation with the relevant local highway authority, approved by the Secretary of State for the following locations—
Great North Road, between A428 and Nelson Road;
Cambridge Road, between Station Road and A428;
Park Street East, Dry Drayton;
Brook Lane, Coton; and
St Neots Road, Sandy.
The operation phase local traffic monitoring scheme must include—
a survey to assess baseline traffic levels at the locations listed in sub-paragraph (1)(a) to (e);
an operation F1phase traffic survey at the locations listed in sub-paragraph (1)(a) to (e) within the first year and fifth year following the date on which the authorised development is fully completed and open for traffic to assess the changes in traffic from the baseline;
the methodology to be used to collect the required data;
the periods over which operation F2phase traffic is to be monitored; and
proposals for the submission of the survey data collected and an interpretative report to be provided to the relevant local highway authority.
The scheme approved under sub-paragraph (1) must be implemented by the undertaker unless otherwise agreed in writing with the Secretary of State following consultation with the relevant local highway authority.
Annotations
Textual amendments
- F1
Word in Sch. 2 para. 23(2)(b) inserted (17.1.2023) by The A428 Black Cat to Caxton Gibbet (Correction) Order 2023 (S.I. 2023/40), art. 1, Sch.
- F2
Word in Sch. 2 para. 23(2)(d) inserted (17.1.2023) by The A428 Black Cat to Caxton Gibbet (Correction) Order 2023 (S.I. 2023/40), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 23 in force at 8.9.2022, see art. 1