Article 7 Application of the 1990 ActI1
England and Wales
This article applies where the Order land is used for the temporary works.
Where this article applies, section 57(2) (planning permission required for development) of the 1990 Act applies as if the development consent granted by this Order were planning permission granted for a limited period.
In this article, “the temporary works” means—
those works described for Work Nos. 10 to 11, 21, 25, 28, 47, 59, 65, 68, 85, 92, 106 and 126 to 128 in Schedule 1; or
temporary works carried out as part of “other associated development” in connection with the Work Nos. in Schedule 1.
Annotations
Textual amendments
- F1
Art. 7(3) substituted (12.1.2026) by The A46 Newark Bypass Development Consent (Correction) Order 2026 (S.I. 2026/16), art. 1, Sch.
Commencement
- I1
Art. 7 in force at 22.10.2025, see art. 1