Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England and Wales
| (1) Plot reference number shown on Land Plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
|---|---|---|
| Land Plans – Sheet 1 | ||
| 1/1n | Temporary access and working area to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/5e | Temporary access and working room to facilitate Work No. 6. | Work No. 6 |
| 1/5f | Temporary access to implement new road signage. | Ancillary |
| 1/5l | Temporary access to the river for deploying safety boat in association with Work No. 7. | Work No. 7 |
| 1/5p | Temporary access for the construction of a new bridge to carry the A46 over the River Trent, including deployment of a safety boat in association with Work No. 7. | Work No. 7 |
| 1/5q | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/7a | Temporary working space to tie in with the construction of the new Farndon Roundabout. | Ancillary |
| 1/10a | Temporary works area and access to facilitate the construction of the new Farndon Roundabout. | Work No. 10 |
| 1/10b | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/12a | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/12b | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/13a | Temporary storage, welfare unit and access to Work Nos. 6 and 7; and temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work Nos. 3, 6, 7 and 127 |
| 1/14a | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/14b | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/14c | Access to Work No. 3 to accommodate bridleway diversion. | Work No. 3 |
| 1/15a | Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3 |
| 1/17a | Temporary storage, welfare unit and access to Work Nos. 6 and 7; and temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2. | Work No. 3, 6, 7 and 127 |
| 1/18a | Temporary access to the river for deploying safety boat in association with Work No. 7. | Work No. 7 |
| 1/18d | Temporary access to the river for deploying safety boat in association with Work No. 7. | Work No. 7 |
| Land Plans – Sheet 2 | ||
| 2/2j | Temporary access for the construction of a new bridge to carry the A46 over the railway line; temporary access for monitoring the railway line in association with Work No. 26; diversion of 11kV electricity distribution cables to underground buried cable; and diversion of electronic communications equipment. | Work Nos. 26, U3 and U4 |
| 2/2k | Temporary access for the construction of a new bridge to carry the A46 over the railway line; and temporary access for monitoring the railway line in association with Work No. 26. | Work No. 26 |
| 2/2m | Temporary access for the construction of a new bridge to carry the A46 over the railway line; temporary access for monitoring the railway line in association with Work No. 26; diversion of 11kV electricity distribution cables to underground buried cable; and diversion of electronic communications equipment. | Work No. 26, U3 and U4 |
| 2/2p | Temporary access to Work No. 27. | Work No. 27 |
| 2/3a | Temporary working room for Work Nos. 22 and 24. | Work Nos. 22 and 24 |
| 2/5a | Temporary access for clearing of Old Trent Dyke for installation of Work No. 23. | Work No. 23 |
| 2/5b | Temporary access for clearing of Old Trent Dyke for installation of Work No. 23. | Work No. 23 |
| 2/7a | Temporary storage, welfare unit and access to facilitate construction of access tracks, the A46 dual carriageway and a new bridge to carry the A46 over the railway line. | Work Nos. 28, 26, 4 and 29 |
| 2/7c | Temporary access to Work No. 4. | Work No. 4 |
| Land Plans – Sheet 3 | ||
| 3/1u | Temporary works area to facilitate widening of railway line to facilitate A46 construction. | Work No. 58 |
| 3/2e | Temporary construction compound. | Work No. 53 |
| 3/2ff | Access for monitoring railway line in association with Work No. 58. | Work No. 58 |
| 3/2g | Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory. | Work No. 49 |
| 3/2g4 | Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory. | Work No. 49 |
| 3/2gg | Access for monitoring railway line in relation to Work No. 58. | Work No. 58 |
| 3/2nn | Temporary access to Work No. 4. | Work No. 4 |
| 3/2r | Temporary access to Work No. 32. | Work No. 32 |
| 3/2x | Temporary Access for monitoring railway line in relation to Work No. 58. | Work No. 58 |
| 3/4e | Temporary working space for environmental mitigation and access to utilities. | Ancillary |
| 3/7a | Access to Work No. 4. | Work No. 4 |
| 3/10d | Temporary working area for environmental mitigation works. | Environmental Mitigation |
| 3/11a | Temporary construction compound. | Work No. 53 |
| 3/11c | Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory. | Work No. 49 |
| 3/11e | Temporary construction compound. | Work No. 53 |
| 3/13a | Working area for environmental mitigation works. | Environmental Mitigation |
| 3/14a1 | Temporary working area and access for turning circle for works vehicles. | Ancillary |
| 3/14b1 | Access and working room to facilitate the construction of Work No. 51 | Work No. 51 |
| 3/14h | Access to Work No. 49; and temporary working space for environmental mitigation. | Work No. 49 Environmental Mitigation |
| Land Plans – Sheet 4 | ||
| 4/2e | Temporary access for the construction of a new bridge to carry the A46 over the River Trent and a temporary bridge to accommodate movement of plant and materials to temporary compound; and temporary access for construction of attenuation basins and drainage infrastructure. | Work Nos. 63, 64 and 67 |
| 4/2g | Access for deployment of safety boat in the River Trent and working area associated with Work No. 64. | Work No. 64 |
| 4/2k | Access for deployment of safety boat in the River Trent and working area associated with Work No. 64. | Work No. 64 |
| 4/2o | Access for deployment of safety boat in the River Trent and working area associated with Work No. 64. | Work No. 64 |
| 4/2p | Access for deployment of safety boat in the River Trent and working area associated with Work No. 64. | Work No. 64 |
| 4/2q | Access for deployment of safety boat in the River Trent and working area associated with Work No. 64. | Work No. 64 |
| 4/5d | Temporary access to Work No. 71. | Work No. 71 |
| 4/5h | Temporary access for the construction of a new bridge to carry the A46 over the River Trent; temporary works area, welfare unit and access to facilitate the construction of a new bridge parallel to Nether Lock Viaduct; and access for monitoring railway line in relation to Work Nos. 64 and 65. | Work Nos. 64 and 65 |
| 4/7g | Temporary works area, welfare unit and access to facilitate the construction of a new bridge parallel to Nether Lock Viaduct. | Work No. 65 |
| 4/7h | Temporary construction compound. | Work No. 71 |
| 4/7i | Temporary construction compound. | Work No. 71 |
| 4/8a | Temporary construction compound and access between construction compound and works. | Work Nos. 62 and 63 |
| 4/8c | Temporary construction compound. | Work No. 71 |
| 4/11a | Temporary access to Work No. 71. | Work No. 71 |
| Land Plans – Sheet 5 | ||
| 5/1d | Working room and access to tie in with new roundabout layout. | Ancillary |
| 5/1m | Working room and access to tie in with new roundabout layout. | Ancillary |
| 5/3d | Access for potential reprofiling of drainage ditches. | Ancillary |
| 5/3h | Working room and access to tie in with new roundabout layout. | Ancillary |
| 5/3i | Working room and access to tie in with new roundabout layout. | Ancillary |
| 5/3j | Access for potential reprofiling of drainage ditches. | Ancillary |
| 5/7d | Temporary working space for environmental mitigation. | Ancillary |
| 5/8a1 | Temporary working space for environmental mitigation. | Ancillary |
| 5/17d | Temporary construction compound and laydown area. | Work Nos. 114 and 106 |
| Land Plans – Sheet 6 | ||
| 6/1c | Temporary working space for environmental mitigation. | Ancillary |
| 6/2b | Temporary working space for environmental mitigation. | Ancillary |
| 6/2d | Temporary working space for environmental mitigation. | Ancillary |
| 6/4b | Temporary working space and access to facilitate realignment of Drove Lane and tie into the new Winthorpe Roundabout. | Work No. 115 |
| 6/6a1 | Temporary working space for environmental mitigation. | Ancillary |
| 6/6c | Temporary storage and lay-down area to facilitate construction of the new Winthorpe Roundabout. | Work No. 111 |
| 6/6c1 | Temporary working space for environmental mitigation. | Ancillary |
| 6/6d | Temporary working space for environmental mitigation. | Ancillary |
| 6/7c | Temporary storage, lay-down area, access and working area to facilitate construction of the new Winthorpe Roundabout and the construction of a temporary access track. | Work Nos. 120 and 117 |
| 6/8a | Temporary access for construction of new signage. | Work No. 121 |
| Land Plans – Sheet 7 | ||
| 7/2b | Temporary access and working room to facilitate the construction of an access track and floodplain compensation area. | Work Nos. 122 and 125 |
Annotations
Commencement
- I1
Sch. 7 in force at 22.10.2025, see art. 1