The A585 Windy Harbour to Skippool Highway Development Consent Order 2020
S.I. 2020/402 · Made 9 April 2020
Infrastructure Planning
Made 9th April 2020
Coming into force 30th April 2020
The application was examined by a single appointed person (appointed by the Secretary of State) in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The single appointed person, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report and recommendation to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn, and the report of the single appointed person, has decided to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 117, 120 and 122 of, and paragraphs 1 to 3, 10 to 15, 17, 19 to 23, 26, 30A, 30B, 33, 36 and 37 of Part 1 of Schedule 5 to the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f2
-
S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572, S.I. 2018/378 and S.I. 2019/734.
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc. granted by the Order
- 4Maintenance of authorised development
- 5Maintenance of drainage works
- 6Limits of deviation
- 7Benefit of Order
- 8Consent to transfer benefit of Order
- Part 3: STREETS
- 9Application of the 1991 Act
- 10Construction and maintenance of new, altered or diverted streets
- 11Classification of roads etc.
- 12Temporary stopping up and restriction of use of streets
- 13Permanent stopping up and restriction of use of streets and private means of access
- 14Access to works
- 15Clearways
- 16Traffic regulation
- Part 4: SUPPLEMENTAL POWERS
- 17Discharge of water
- 18Protective work to buildings
- 19Authority to survey and investigate the land
- Part 5: POWERS OF ACQUISITION AND POSSESSION
- 20Compulsory acquisition of land
- 21Compulsory acquisition of land – incorporation of the mineral code
- 22Time limit for exercise of authority to acquire land compulsorily
- 23Compulsory acquisition of rights and restrictive covenants
- 24Private rights over land
- 25Modification of Part 1 of the 1965 Act
- 26Application of the 1981 Act
- 27Acquisition of subsoil or airspace only
- 28Rights under or over streets
- 29Temporary use of land for carrying out the authorised development
- 30Temporary use of land for maintaining the authorised development
- 31Statutory undertakers
- 32Apparatus and rights of statutory undertakers in stopped up streets
- 33Recovery of costs of new connections
- Part 6: OPERATIONS
- 34Felling or lopping of trees and removal of hedgerows
- Part 7: MISCELLANEOUS AND GENERAL
- 35Deemed Marine Licence
- 36Application of landlord and tenant law
- 37Trees subject to tree preservation orders
- 38Operational land for purposes of the 1990 Act
- 39Defence to proceedings in respect of statutory nuisance
- 40Protection of interests
- 41Certification of documents, etc.
- 42Service of notices
- 43Arbitration
- 44Crown rights
- Signature
- Schedule 1AUTHORISED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- Part 1: REQUIREMENTS
- Interpretation
- 1Paragraph 1
- Time limits
- 2Paragraph 2
- Detailed design
- 3Paragraph 3
- Construction and handover environmental management plans
- 4Paragraph 4
- Landscaping
- 5Paragraph 5
- Contaminated land and groundwater
- 6Paragraph 6
- Protected species
- 7Paragraph 7
- Surface and foul water drainage
- 8Paragraph 8
- Archaeological remains
- 9Paragraph 9
- Traffic management
- 10Paragraph 10
- Amendments to approved details
- 11Paragraph 11
- Fencing
- 12Paragraph 12
- Details of consultation
- 13Paragraph 13
- Temporary compensatory flood storage system
- 14Paragraph 14
- Soil survey and mitigation plan
- 15Paragraph 15
- Part 2: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- Applications made under requirements
- 16Paragraph 16
- Further information
- 17Paragraph 17
- Register of requirements
- 18Paragraph 18
- Anticipatory steps towards compliance with any requirement
- 19Paragraph 19
- Schedule 3: CLASSIFICATION OF ROADS, ETC.
- 1TRUNK ROADS
- 2CLASSIFIED ROADS
- 3UNCLASSIFIED ROADS
- 4OTHER PUBLIC RIGHTS OF WAY
- 5ROADS TO BE DE-TRUNKED
- 6SPEED LIMITS
- 7REVOCATIONS AND VARIATIONS OF EXISTING TRAFFIC REGULATION ORDERS
- 8NEW TRAFFIC REGULATION ORDERS SOUGHT
- Schedule 4: PERMANENT STOPPING UP OF STREETS AND PRIVATE MEANS OF ACCESS
- 1PUBLIC RIGHTS OF WAY OR HIGHWAY TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 2PUBLIC RIGHTS OF WAY OR HIGHWAY TO BE STOPPED UP AND FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- 3PRIVATE MEANS OF ACCESS TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 4PRIVATE MEANS OF ACCESS TO BE STOPPED UP AND FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- Schedule 5LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- Schedule 6: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
- Compensation enactments
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- Application of Part 1 of the 1965 Act
- 4Paragraph 4
- 5Paragraph 5
- Schedule 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 8: DEEMED MARINE LICENCE
- 1INTRODUCTORY
- Part 2: LICENSED ACTIVITIES
- 3Paragraph 3
- 4Paragraph 4
- Part 3: ENFORCEMENT
- 5Paragraph 5
- Part 4: CONDITIONS
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- Schedule 9: HEDGEROWS AND TREES
- 1HEDGEROWS
- 2TREES SUBJECT TO TREE PRESERVATION ORDERS
- Schedule 10: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWAGE UNDERTAKERS
- 1Paragraph 1
- 2Paragraph 2
- On street apparatus
- 3Paragraph 3
- Apparatus in stopped up streets
- 4Paragraph 4
- Protective works to buildings
- 5Paragraph 5
- Acquisition of land
- 6Paragraph 6
- Removal of apparatus
- 7Paragraph 7
- Facilities and rights for alternative apparatus
- 8Paragraph 8
- Retained apparatus
- 9Paragraph 9
- Expenses and costs
- 10Paragraph 10
- 11Paragraph 11
- Cooperation
- 12Paragraph 12
- 13Paragraph 13
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- Part 3: FOR THE PROTECTION OF CADENT GAS LTD AS GAS UNDERTAKER
- 18Application
- 19Interpretation
- 20On Street Apparatus
- 21Apparatus of Cadent in stopped up streets
- 22Protective works to buildings
- 23Acquisition of land
- 24Removal of apparatus
- 25Facilities and rights for alternative apparatus
- 26Retained apparatus: protection of Cadent
- 27Expenses
- 28Indemnity
- 29Enactments and agreements
- 30Co-operation
- 31Access
- 32Arbitration
- 33Notices
- Schedule 11DOCUMENTS TO BE CERTIFIED
- Explanatory note