1/07a, 1/07f, 1/07lRequired to provide construction working area for replacement culvert and for the diversion of electric cables and associated auxiliary cables

Work No.6

Work No.115

1/05a, 1/05bRequired to provide construction working area for replacement culvert and dwarf wall and for the diversion of a water pipeline

Work No.34

Work No.115

Work No.122

1/05cRequired for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated wasteAll Works
1/05dRequired to provide construction working area for the combined footway/cycleway and for the diversion of a water pipeline

Work No.17

Work No.34

1/30a, 1/34aRequired to provide an improved private means of access and for the diversion of a water pipeline and for the diversion of electric cables and associated auxiliary cables

Work No.23

Work No.24

Work No.30

Work No.31

1/30b, 1/34b, 1/34f, 1/34gRequired for the diversion of a water pipeline and for the diversion of electric cables and associated auxiliary cables

Work No.24

Work No.30

Work No.31

Land Plans – Sheet 3
3/01aRequired to provide a construction working area and improved private means of accessWork No.97
Land Plans – Sheet 4
4/02cRequired to provide a construction working area for highway boundary fencing and for the diversion of electric cables and associated auxiliary cables

Work No.36

Work No.40

4/02b, 4/02c, 4/03a, 4/02d, 4/06c, 4/06d, 4/06h, 4/06e, 4/06g, 4/08b, 4/08e, 4/08gRequired to provide a construction working area for highway boundary fencingWork No.40
4/06d. 4/06h, 4/06gRequired to provide a construction working area for highway boundary fencing and for the diversion of electric cables and associated auxiliary cables

Work No.40

Work No.42

4/06fRequired to provide a flood mitigation areaWork No.98
4/08aRequired to provide a flood mitigation areaWork No.111
4/08dRequired to provide a flood mitigation areaWork No.110
4/08fRequired to provide a flood mitigation areaWork No.109
4/08lRequired to provide a construction working area and for drainage worksWork No.113
4/10a, 4/12Required for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated wasteAll Works
Land Plans – Sheet 5
5/01aRequired to provide a construction working area (including for construction material storage, construction access and storage of plant) and for the diversion of water pipelinesAll Works
5/01cRequired to provide a construction working area for highway boundary fencing and for the diversion of a water pipeline

Work No.48

Work No.53

Work No.55

Work No.58

5/01eRequired to provide a temporary access for main construction compoundAll Works
5/01f, 5/01k, 5/01iRequired to provide a construction working area for highway boundary fencing

Work No.57

Work No.58

Work No.59

5/01h, 5/06jRequired for the diversion of a water pipeline and construction working area for culvert

Work No.61

Work No.62

5/05bRequired for the diversion of a water pipelineWork No.60
5/06aRequired to provide a borrow pit area and for the diversion of electric cables and associated auxiliary cables and water pipeline

Work No.63

Work No.61

Work No.64

5/06cRequired to provide a construction working area for highway boundary fencing and for the diversion of water pipelines and electric cables and associated auxiliary cables

Work No.58

Work No.59

Work No.61

5/06iRequired to provide a construction working area for the bridge and for the diversion of electric cables and associated auxiliary cables

Work No.58

Work No.70

Work No.64

5/06dRequired to provide a construction working area for highway boundary fencing and for the diversions of water pipelines and electric cables and associated auxiliary cables

Work No.58

Work No.60

Work No.61

Work No.72

5/06bRequired to provide a borrow pit area and for the diversion of electric cables and associated auxiliary cables and for diversion of a gas pipeline and for the diversion of water pipelines

Work No.60

Work No.61

Work No.69

Work No.72

Work No.78

5/06hRequired to provide a construction working area for the bridge and for the diversion of electric cables and associated auxiliary cables and gas pipeline

Work No. 69

Work No.70

Work No.72

5/07c, 5/15aRequired for the diversion of a water pipelineWork No.61
5/12Required to provide an improved private means of access and for the diversion of a gas pipeline

Work No.67

Work No.68

5/15, 5/07b, 5/07dRequired for the diversion of a water pipelineWork No.60
5/09e, 5/09c, 5/09d, 5/09bRequired to provide an improved private means of access and for the diversion of electric cables and associated auxiliary works and for the diversion of a gas pipeline and for the diversion for telecommunications cables

Work No.71

Work No.72

Work No.73

Work No.74

Work No.75

Work No.76

Work No.120

Land Plans – Sheet 6
6/43aRequired to provide a construction working area for highway boundary fencingWork No.87
Land Plans – Sheet 7
7/01aRequired to provide a construction working area for highway boundary fencingWork No.58
7/02dRequired to provide a construction working area for highway boundary fencing and for the diversion of a water pipeline

Work No.58

Work No.77

7/06b, 7/06c, 7/08a, 7/07aRequired to provide a construction working area for highway boundary fencing

Work No.58

Work No.90

Work No.93

7/07b, 7/07cRequired to provide a construction working area for highway boundary fencing and pavement wideningWork No.58
7/04aRequired to provide a construction working area for highway boundary fencing and culvert

Work No.58

Work No.91

Land Plans – Sheet 8
8/02dRequired to provide a construction working area for highway boundary fencingWork No.29
8/02e, 8/04Required to provide a habitat mitigation areaAll Works