Paragraph 24 Dates of final commissioning, completion of construction and cessationI1

England, Wales and Scotland

(1)

The undertaker must notify the relevant planning authority in writing of the date of final commissioning as soon as reasonably practicable and in any event within three months after the occurrence of that date.

(2)

The undertaker must notify the relevant planning authority in writing of the date of completion of construction as soon as reasonably practicable and in any event within three months after the occurrence of that date.

(3)

The undertaker must notify the relevant planning authority in writing of the date the authorised development permanently ceases to generate power on a commercial basis as soon as reasonably practicable and in any event within three months after the occurrence of that date.

Annotations

Commencement

I1

Sch. 2 para. 24 in force at 10.10.2019, see art. 1