Paragraph 58 I1
England, Wales and Scotland
(1)
The licence holder must notify the Conservancy Authority of the need to update the Humber Maintenance Dredge Protocol and Water Framework Directive Compliance Baseline Document 2011 or any document replacing it (“the baseline document”), to incorporate the dredging and disposal of dredged material consented.
(2)
The updated baseline document must be submitted with any subsequent application made to the MMO for maintenance dredging activities.
Annotations
Commencement
- I1
Sch. 8 para. 58 in force at 29.10.2014, see Introductory Text