The Able Marine Energy Park Development Consent Order 2014
S.I. 2014/2935 · Made 13 January 2014 · Extends to England, Wales and Scotland
Infrastructure Planning
Harbours, Docks, Piers And Ferries
Made 13th January 2014
Laid before Parliament 10th February 2014
Coming into force 29th October 2014
A Panel of three members (“the Panel”) was appointed by the Secretary of State in accordance with Chapter 2 of Part 6 of the 2008 Act. The Panel examined the application in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The Panel has considered the representations made and not withdrawn and the application, together with accompanying documents, and has submitted a report to the Secretary of State in accordance with section 74 of the 2008 Act.
The Secretary of State, having considered the representations made and not withdrawn, and the report of the Panel, has decided to make an Order granting development consent for the development described in the application and consent for ancillary works with modifications which, in the opinion of the Secretary of State, do not make any substantial change to the proposals comprised in the application.
The Order authorises the compulsory acquisition of land which has been acquired by statutory undertakers for the purposes of their undertakings. Representations were made by the statutory undertakers concerned about the application for the Order before the completion of the examination of the application, the representations contained objections to the compulsory acquisition of the land and the objections have not been withdrawn.
The Order will not come into force until it has been laid before Parliament and has been brought into operation in accordance with the provisions of the Statutory Orders (Special Procedure) Acts 1945 and 1965f4.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 122 of, and paragraphs 1 to 3, 10 to 17, 24, 26, 30A to 32, 32B to 34, 36, and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264, as amended by S.I. 2010/493, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, and S.I. 2013/522.
- f2
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f3
-
S.I. 2010/103, as amended by S.I. 2010/635.
- f4
-
1945 c.18 (9 & 10 Geo 6), and 1965 c. 43. Section 1 was repealed in part by the Statute Law (Repeals) Act 1974. The remainder amends the Statutory Orders (Special Procedure) Act 1945, ss 3(1), (3), 4(1), (2), 9(a), 10 (3).
Contents
- Part 1: PRELIMINARY
- 1Citation
- 2Interpretation
- 3Incorporation of the 1847 Act
- 4Modification of enactments
- Part 2: PRINCIPAL POWERS
- 5Development consent etc. granted by the Order
- 6Limits of deviation
- 7Period for completion of work
- 8Jurisdiction of the Harbour Authority
- 9Agreements entered into by the Company etc.
- 10Maintenance of authorised development
- 11Provision of works
- 12Benefit of Order
- 13Consent to transfer benefit of Order
- 14Guarantees in respect of payment
- Part 3: STREETS
- 15Street works
- 16Temporary stopping up of streets
- 17Access to works
- 18Agreements with street authorities
- 19Public rights of way
- Part 4: SUPPLEMENTAL POWERS
- 20Discharge of water
- 21Protective work to buildings
- 22Authority to survey and investigate the land
- 23Tidal works not to be executed without approval of Secretary of State
- 24Abatement of works abandoned or decayed
- 25Survey of tidal works
- 26Lights on tidal works etc. during construction
- 27Provision against danger to navigation
- 28Permanent lights on tidal works
- 29Power to appropriate
- Part 5: POWERS OF ACQUISITION
- 30Compulsory acquisition of land
- 31Power to override easements and other rights
- 32Compulsory acquisition of land – incorporation of the mineral code
- 33Time limit for exercise of authority to acquire land compulsorily
- 34Compulsory acquisition of rights
- 35Private rights of way
- 36Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 37Acquisition of subsoil only
- 38Acquisition of part of certain properties
- 39Rights under or over streets
- 40Temporary use of land for carrying out the authorised development
- 41Temporary use of land for maintaining authorised development
- 42Statutory undertakers
- 43Recovery of costs of new connections
- Part 6: MISCELLANEOUS AND GENERAL
- 44Deemed marine licence
- 45Felling or lopping of trees
- 46Trees subject to tree preservation orders
- 47Railway and navigation undertakings
- 48Arrangements with Her Majesty’s Revenue and Customs
- 49Application of landlord and tenant law
- 50Operational land for purposes of the 1990 Act
- 51Defence to proceedings in respect of statutory nuisance
- 52Protection of interests
- 53Saving for Trinity House
- 54Planning etc. jurisdiction
- 55Certification of plans etc
- 55ACertification of further environmental documents
- 55BCertification of additional plans etc.
- 56Service of notices
- 57Arbitration
- 58Requirements - appeals
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- Chapter: NATIONALLY SIGNIFICANT INFRASTRUCTURE PROJECT
- 1Paragraph 1
- ASSOCIATED DEVELOPMENT
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- Schedule 2STREETS SUBJECT TO STREET WORKS
- Schedule 3STREETS TO BE TEMPORARILY STOPPED UP
- Schedule 4ACCESS TO WORKS
- Schedule 5FOOTPATHS TO BE STOPPED UP
- Schedule 6LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 7TREES SUBJECT TO TREE PRESERVATION ORDERS
- Schedule 8: DEEMED MARINE LICENCE
- Part 1: INTRODUCTORY
- Interpretation
- 1Paragraph 1
- Addresses
- 2Paragraph 2
- Part 2: LICENSED ACTIVITIES
- 3Paragraph 3
- Construction of the quay
- 4Paragraph 4
- Temporary dolphins
- 5Paragraph 5
- Berthing pocket infill
- 6Paragraph 6
- Pumping station
- 7Paragraph 7
- Compensation site creation
- 8Paragraph 8
- Rock armour
- 9Paragraph 9
- Temporary bog matting
- 10Paragraph 10
- Capital dredging
- 11Paragraph 11
- Maintenance dredging
- 12Paragraph 12
- Part 3: ENFORCEMENT
- 13Paragraph 13
- Part 4: CONDITIONS
- General conditions
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Paragraph 23
- Project wide conditions
- 24Paragraph 24
- 25Paragraph 25
- 26Paragraph 26
- 27Paragraph 27
- 28Paragraph 28
- 29Paragraph 29
- 30Paragraph 30
- 31Paragraph 31
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- 36Paragraph 36
- Piling conditions
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- General dredging and disposal conditions
- 44Paragraph 44
- 45Paragraph 45
- 46Paragraph 46
- 47Paragraph 47
- 48Paragraph 48
- 49Paragraph 49
- Capital dredging and disposal conditions
- 50Paragraph 50
- 51Paragraph 51
- 52Paragraph 52
- 53Paragraph 53
- 54Paragraph 54
- Maintenance dredging and disposal conditions
- 55Paragraph 55
- 56Paragraph 56
- 57Paragraph 57
- 58Paragraph 58
- 59Paragraph 59
- 60Paragraph 60
- Placement of rock and gravel materials below mean high water springs
- 61Paragraph 61
- 62Paragraph 62
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- 68Paragraph 68
- 69Paragraph 69
- Schedule 9: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF THE HUMBER CONSERVANCY
- Interpretation
- 1Paragraph 1
- General
- 2Paragraph 2
- Tidal Works: approval of detailed design
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- Discharges, etc.
- 6Paragraph 6
- 7Paragraph 7
- Obstruction in river
- 8Paragraph 8
- Removal etc. of the Conservancy Authority moorings and buoys
- 9Paragraph 9
- Navigational lights, buoys, etc.
- 10Paragraph 10
- Removal of temporary works
- 11Paragraph 11
- Protective action
- 12Paragraph 12
- Abandoned or decayed works
- 13Paragraph 13
- Facilities for navigation
- 14Paragraph 14
- Survey of riverbed
- 15Paragraph 15
- Sedimentation, etc.: remedial action
- 16Paragraph 16
- Indemnity
- 17Paragraph 17
- Entry for survey, etc.
- 18Paragraph 18
- Statutory functions
- 19Paragraph 19
- Operating procedures
- 20Paragraph 20
- Consideration for dredged material
- 21Paragraph 21
- Removal of wrecks and obstructions, etc.
- 22Paragraph 22
- Transfer of benefit of Order
- 23Paragraph 23
- Oil Spillage Plan
- 24Paragraph 24
- Disputes
- 25Paragraph 25
- Part 2: FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
- 26Paragraph 26
- 27Paragraph 27
- 28Paragraph 28
- 29Paragraph 29
- 30Paragraph 30
- Part 3: FOR THE PROTECTION OF THE HIGHWAYS AGENCY
- 31Paragraph 31
- Part 4: FOR THE PROTECTION OF NETWORK RAIL
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- 44Paragraph 44
- 45Paragraph 45
- 46Paragraph 46
- 47Paragraph 47
- Part 5: FOR THE PROTECTION OF C.GEN
- 48Paragraph 48
- 49Paragraph 49
- 50Paragraph 50
- Rosper Road
- 51Paragraph 51
- 52Paragraph 52
- 53Paragraph 53
- 54Paragraph 54
- 55Paragraph 55
- Part 6: FOR THE PROTECTION OF C.RO
- 56Paragraph 56
- 57Paragraph 57
- 58Paragraph 58
- 59Paragraph 59
- 60Paragraph 60
- 61Paragraph 61
- 62Paragraph 62
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- Dredging
- 67Paragraph 67
- Railway
- 68Paragraph 68
- 69Paragraph 69
- Rosper Road
- 70Paragraph 70
- 71Paragraph 71
- Recovery of expenses
- 72Paragraph 72
- 73Paragraph 73
- 74Paragraph 74
- 75Paragraph 75
- Part 7: FOR THE PROTECTION OF PHILLIPS 66 LIMITED
- 76Paragraph 76
- 77Paragraph 77
- 78Paragraph 78
- 79Paragraph 79
- Part 8: FOR THE PROTECTION OF NATIONAL GRID
- 80Paragraph 80
- 81Paragraph 81
- 82Paragraph 82
- 83Paragraph 83
- 84Paragraph 84
- 85Paragraph 85
- 86Paragraph 86
- General
- 87Paragraph 87
- Part 9: FOR THE PROTECTION OF E.ON UK PLC
- 88Paragraph 88
- 89Paragraph 89
- 90Paragraph 90
- The pipelines
- 91Paragraph 91
- General
- 92Paragraph 92
- Part 10: FOR THE PROTECTION OF CENTRICA PLC
- 93Paragraph 93
- 94Paragraph 94
- 95Paragraph 95
- The pipelines
- 96Paragraph 96
- 97Paragraph 97
- Power station access road
- 98Paragraph 98
- General
- 99Paragraph 99
- Part 11: FOR THE PROTECTION OF ANGLIAN WATER
- 100Paragraph 100
- 101Paragraph 101
- 102Paragraph 102
- 103Paragraph 103
- 104Paragraph 104
- 105Paragraph 105
- 106Paragraph 106
- 107Paragraph 107
- Part 12: FOR THE PROTECTION OF BETHANY JAYNE LTD
- 108Paragraph 108
- Part 13: FOR THE PROTECTION OF ROYAL MAIL GROUP LTD
- 109Paragraph 109
- 110Paragraph 110
- Part 14: FOR THE PROTECTION OF ASSOCIATED BRITISH PORTS
- 111Paragraph 111
- 112Paragraph 112
- 113Paragraph 113
- 114Paragraph 114
- 115Paragraph 115
- 116Paragraph 116
- 117Paragraph 117
- 118Paragraph 118
- Part 15: FOR THE PROTECTION OF THE OIL AND PIPELINES AGENCY
- 119Paragraph 119
- 120Paragraph 120
- Part 16: FOR THE PROTECTION OF VPI IMMINGHAM B LIMITED
- 121Application
- 122Interpretation
- 123Regulation of powers over Rosper Road
- 124Paragraph 124
- 125Paragraph 125
- 126Arbitration
- Schedule 10: LIMITS OF HARBOUR
- 1Paragraph 1
- Schedule 11: REQUIREMENTS
- 1Paragraph 1
- Time limits
- 2Paragraph 2
- Stages of the development
- 3Paragraph 3
- Cargo restriction
- 4Paragraph 4
- Detailed design approval
- 5Paragraph 5
- 6Paragraph 6
- Provision of landscaping
- 7Paragraph 7
- Implementation and maintenance of landscaping
- 8Paragraph 8
- Trees
- 9Paragraph 9
- Highway access
- 10Paragraph 10
- Public rights of way
- 11Paragraph 11
- Fencing and other means of enclosure
- 12Paragraph 12
- Surface water drainage
- 13Paragraph 13
- Foul water drainage
- 14Paragraph 14
- River basin management
- 15Paragraph 15
- Contaminated land
- 16Paragraph 16
- Archaeology
- 17Paragraph 17
- Listed building
- 18Paragraph 18
- Environmental management and monitoring plans
- 19Paragraph 19
- 20Paragraph 20
- Programming of Works
- 21Paragraph 21
- Code of construction practice
- 22Paragraph 22
- Design of roads
- 23Paragraph 23
- External lighting
- 24Paragraph 24
- Construction traffic
- 25Paragraph 25
- Control of noise during construction
- 26Paragraph 26
- Control of noise during operation
- 27Paragraph 27
- Control of emissions
- 28Paragraph 28
- Travel plan
- 29Paragraph 29
- Traffic management plan
- 30Paragraph 30
- European protected species
- 31Paragraph 31
- Requirement for consent of Civil Aviation Authority and Ministry of Defence
- 32Paragraph 32
- Flood warning and evacuation plan
- 33Paragraph 33
- Listed buildings
- 34Paragraph 34
- Tall structures
- 35Paragraph 35
- Cooling water intakes and outfalls
- 36Paragraph 36
- Piling
- 37Paragraph 37
- Sedimentation
- 38Paragraph 38
- 39Paragraph 39
- Contaminants and remediation
- 40Paragraph 40
- 41Paragraph 41
- Mitigation site requirements
- 42Paragraph 42
- Environment Agency requirements
- 43Paragraph 43
- 44Paragraph 44
- Requirement for written approval
- 45Paragraph 45
- Explanatory note