Paragraph 11 I1

England, Wales and Scotland

(1)

The licence holder is permitted to carry out capital dredging at the following locations—

(a)

the area within the quay limits to a depth of -6.5 metres Chart Datum;

(b)

the berthing pocket to a depth of -14.5 metres Chart Datum;

(c)

the approach channel to a depth of -9 metres Chart Datum;

(d)

the turning area to a depth of -9 metres Chart Datum;

(e)

the pumping station outfall to a depth of +2.0 metres Chart Datum; and

(f)

the Cherry Cobb Sands breach to a depth of +3.0 metres Chart Datum.

(2)

The materials must be dredged in the approximate quantities and deposited at the locations according to the following table—

LocationMaterialMaximum tonnage per yearDeposit locationTotal licensed tonnage
Area within the quay limitsGravel50,000HU080725,000
Sand110,000
Silt390,000
Clay175,000HU082
The berthing pocketGravel5,000HU0801,835,000
Sand50,000
Silt145,000
Clay535,000HU082
Clay1,100,000The terrestrial area landward of the existing Killingholme Marshes flood defence wall
The approach channelGravel150,000Within the quay limits1,650,000
Gravel150,000HU080
Sand600,000
Silt500,000
Clay250,000HU082
The turning areaGravel35,000HU080250,000
Sand95,000
Silt80,000
Clay40,000HU082
The pumping station outfallSand500HU0808,000
Silt7,500
The Cherry Cobb Sands breachSand2,000If the dredged material is suitable, the area within the proposed managed realignment site10,000
Silt8,000