Paragraph 12 I1

England, Wales and Scotland

(1)

If any tidal work—

(a)

is constructed otherwise than in accordance with the requirements of this Part of this Schedule or with any condition in an approval given pursuant to paragraph 3(4); or

(b)

during construction gives rise to sedimentation, scouring, currents or wave action detrimental to traffic in, or the flow or regime of, the river,

then the Conservancy Authority may by notice in writing require the Harbour Authority at the Harbour Authority’s own expense to comply with the remedial requirements specified in the notice.

(2)

The requirements that may be specified in a notice given under sub-paragraph (1) are—

(a)

in the case of a tidal work to which sub-paragraph (1)(a) applies, such requirements as may be specified in the notice for the purpose of giving effect to the requirements of—

(i)

this Part of this Schedule; or

(ii)

the condition that has been breached; or

(b)

in any case within sub-paragraph (1)(b), such requirements as may be specified in the notice for the purpose of preventing, mitigating or making good the sedimentation, scouring, currents or wave action so far as required by the needs of traffic in, or the flow or regime of, the river.

(3)

If the Harbour Authority does not comply with a notice under sub-paragraph (1), or is unable to do so, the Conservancy Authority may in writing require the Harbour Authority to—

(a)

remove, alter or pull down the tidal work, and where the tidal work is removed to restore the site of that work (to such extent as the Conservancy Authority reasonably requires) to its former condition; or

(b)

take such other action as the Conservancy Authority may reasonably specify for the purpose of remedying the non-compliance to which the notice relates.

(4)

If a tidal work gives rise to environmental impacts over and above those anticipated by any environmental document, the Harbour Authority, in compliance with its duties under any enactment and, in particular, under section 48A of the Harbours Act 1964f1, must take such action as is necessary to prevent or mitigate those environmental impacts and in doing so must consult and seek to agree the necessary measures with the Conservancy Authority.

(5)

If the Conservancy Authority becomes aware that any tidal work is causing an environmental impact over and above those anticipated by any environmental document, the Conservancy Authority must notify the Harbour Authority of that environmental impact, the reasons why the Conservancy Authority believes that the environmental impact is being caused by the tidal work and of measures that the Conservancy Authority reasonably believes are necessary to counter or mitigate that environmental impact.

(6)

The Harbour Authority must implement the measures that the Conservancy Authority has notified to the Harbour Authority or must implement such other measures as the Harbour Authority believes are necessary to counter the environmental impact identified, giving reasons to the Conservancy Authority as to why it has implemented such other measures.

Annotations

Commencement

I1

Sch. 9 para. 12 in force at 29.10.2014, see Introductory Text

Footnotes

f1

1964. c. 40. Section 48A was inserted by the Transport and Works Act 1992 (c. 42), section 63(1) and Schedule 3 para. 6; S.I. 1992/1347, article 2 and Schedule.