Paragraph 83 I1
England, Wales and Scotland
Subject to the following provisions of this paragraph, the undertaker must repay to National Grid on demand all charges, costs and expenses reasonably incurred by National Grid in connection with, the inspection and protection of any apparatus which may be required in consequence of the execution of any such works as are required under this Part of this Schedule including—
the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works if applicable; and
the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.
Annotations
Commencement
- I1
Sch. 9 para. 83 in force at 29.10.2014, see Introductory Text