Paragraph 18 I1

England, Wales and Scotland

(1)

No stage of the authorised development is to commence until a written management plan for the Killingholme North Low Lighthouse (‘the building’) has been submitted to and approved by the relevant planning authority, including the following—

(a)

a structural survey to be submitted to and approved by the relevant planning authority;

(b)

implementation of mitigation measures;

(c)

a schedule of repair works that ensure the long-term survival of the building;

(d)

an implementation timetable for all stages of work including timings to ensure that the mitigation measures and repair work are undertaken and completed in accordance with the plan;

(e)

monitoring arrangements with the relevant planning authority, including notification of the commencement of work;

(f)

details of all contractors to be involved in implementation of works to the building; and

(g)

details of the use of the building including proposals for community access and interpretation.

(2)

The management plan must be implemented as approved.

Annotations

Commencement

I1

Sch. 11 para. 18 in force at 29.10.2014, see Introductory Text