Paragraph 18 I1
England, Wales and Scotland
No stage of the authorised development is to commence until a written management plan for the Killingholme North Low Lighthouse (‘the building’) has been submitted to and approved by the relevant planning authority, including the following—
a structural survey to be submitted to and approved by the relevant planning authority;
implementation of mitigation measures;
a schedule of repair works that ensure the long-term survival of the building;
an implementation timetable for all stages of work including timings to ensure that the mitigation measures and repair work are undertaken and completed in accordance with the plan;
monitoring arrangements with the relevant planning authority, including notification of the commencement of work;
details of all contractors to be involved in implementation of works to the building; and
details of the use of the building including proposals for community access and interpretation.
The management plan must be implemented as approved.