Paragraph 3 I1
England, Wales and Scotland
Before—
submitting any plans and sections for any tidal work to the Secretary of State for approval under article 23 (tidal works not to be constructed without approval of the Secretary of State);
agreeing a vessel movement management plan with the MMO under paragraph 16 of Schedule 8 (deemed marine licence);
agreeing a dredge and disposal strategy with the MMO under paragraph 45 of Schedule 8;
seeking approval from the relevant planning authority for any alteration of the drawings under paragraph 6 of Schedule 11 (requirements) that affects the area below mean high water mark;
seeking approval from the relevant planning authority for any external lighting details under paragraph 24 of Schedule 11 that affect the area below mean high water mark;
commencing any operation for the construction of a tidal work where approval of the Secretary of State under article 23 is not required; or
commencing any operation for the maintenance of a tidal work,
the Harbour Authority must submit to the Conservancy Authority plans and sections of the tidal work or operation and such further particulars as the Conservancy Authority may, within 28 days from the day on which plans and sections are submitted under this sub-paragraph, reasonably require.
Before submitting for approval, agreement or otherwise as provided by this Order any document specified in columns (1) and (2) of the following Table, the Harbour Authority must submit a copy to the Conservancy Authority for approval of the matters specified in column (3) of the Table and must consult the Conservancy Authority on the remainder of each such document.
TABLE
(1) Document | (2) Provision of Order | (3) Provision requiring Conservancy Authority approval |
|---|---|---|
| Marine environmental management and monitoring plan | Schedule 11, paragraph 19 | Provision relating to monitoring equipment fixed to buoys |
| Works schedule | Schedule 8, paragraph 24 | None |
| Active monitoring scheme | Schedule 8, paragraph 39 | Provision relating to the locations of active monitoring buoys |
| Stages of the development scheme | Schedule 11, paragraph 3 | None |
| Code of construction practice | Schedule 11, paragraph 22 | None |
No application for the Secretary of State’s approval under article 23 is to be made in respect of a tidal work until plans and sections in respect of that tidal work submitted under sub-paragraph (1) have been approved by the Conservancy Authority.
Any tidal work not requiring the Secretary of State’s approval under article 23 must not be constructed, and no tidal work is to be maintained, except in accordance with such plans as may be approved in writing by the Conservancy Authority or determined under paragraph 25.
Any approval of the Conservancy Authority required under this paragraph must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as the Conservancy Authority may make for the protection of—
traffic in, or the flow or regime of, the river;
the use of its operational land or the river for the purposes of performing its functions; or
the performance of any of its functions connected with environmental protection.
Requirements made under sub-paragraph (5) may include conditions as to—
the relocation, provision and maintenance of works, moorings, apparatus and equipment necessitated by the tidal work; and
the expiry of the approval if the Harbour Authority does not commence construction of the tidal work approved within a prescribed period.
Subject to sub-paragraphs (8) and (9), any such approval is deemed to have been refused if it is neither given nor refused within 42 days of the specified day.
Before making a decision on any such approval, the Conservancy Authority must take into account any opinion on plans and sections provided to it by the Environment Agency.
Accordingly, an approval of the Conservancy Authority under this paragraph is not deemed to have been unreasonably withheld if approval within the time limited by sub-paragraph (7) has not been given pending the outcome of any consultation on the approval in question that the Conservancy Authority is obliged in the proper exercise of its functions to carry out provided that during the course of such consultation, the Conservancy Authority has acted with all due expedition.
In this paragraph “the specified day” means, in relation to any tidal work—
the day on which plans of that work are submitted to the Conservancy Authority under sub-paragraph (1); or
the day on which the Harbour Authority provides the Conservancy Authority with all such particulars of the work as have been reasonably requested by the Conservancy Authority under that sub-paragraph;
whichever is later.
Whenever the Harbour Authority provides the Secretary of State with an environmental document it must at the same time send a copy to the Conservancy Authority.