The licence holder is permitted to deposit rock armouring to the northern extent of the flood defence breach at Cherry Cobb Sands under the following conditions—

(a)

the quantity of rock to be placed must be agreed with the MMO at least 4 weeks prior to works commencement;

(b)

the exact location must be agreed with the MMO at least 4 weeks prior to works commencement; and

(c)

the placement of rock armouring must only be carried out in accordance with the agreed location and rock quantity.