Paragraph 54 I1

England, Wales and Scotland

(1)

The licence holder must employ methods to minimise resuspension of sediment during the construction and dredging operations.

(2)

The methodology must be submitted to the MMO at least 4 weeks prior to the commencement of the works.

(3)

Written approval by the MMO is required prior to works commencing.