Paragraph 125 F1
England, Wales and Scotland
Insofar as the construction of the OCGT authorised development is or may be undertaken concurrently with the Able authorised development, the undertaker must—
co-operate with VPI with a view to ensuring—
the co-ordination of construction programming and the carrying out of works; and
that access for the purposes of constructing the respective authorised developments is maintained for the undertaker and VPI and their respective contractors; and
use reasonable endeavours to avoid any conflict arising from the carrying out of the respective authorised developments.