OpenLegislation

Paragraph 91 InterpretationI1

England and Wales

Without limitation on the scope of paragraph 90 the requirements which North East Lincolnshire Council may make include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including any new works as well as alterations to existing works) as are reasonably necessary—

(a)

to safeguard any drainage work against damage; or

(b)

to secure that the efficiency of any ordinary watercourse for flood defence or land drainage purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of the specified work.

Annotations

Commencement

I1

Sch. 4 para. 91 in force at 25.10.2024, see art. 1