Paragraph 2 Applications made under requirementsI1
England and Wales
Where an application has been made to the relevant planning authority for any consent, agreement or approval required pursuant to a requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period of 13 weeks beginning with—
(a)
the day immediately following that on which the application is received by the relevant planning authority; or
(b)
such longer period as may be agreed by the undertaker and the relevant planning authority.
Annotations
Commencement
- I1
Sch. 11 para. 2 in force at 11.10.2023, see art. 1