Paragraph 17 Restoration of land used temporarily for constructionI1

England and Wales

Any land landward of MLWS which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated within six months of completion of the relevant stage of the onshore works in accordance with details submitted to and approved by the relevant planning authority under requirement 10 (code of construction practice).

Annotations

Commencement

I1

Sch. 2 para. 17 in force at 11.10.2023, see art. 1