Paragraph 1 Applications made under RequirementI1
England, Wales and Scotland
Where an application has been made to the relevant planning authority for any agreement or approval required pursuant to a Requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision including the reasons on the application, within a period of 8 weeks beginning with—
(a)
the day immediately following that on which the application is received by the authority; or
(b)
such longer period as may be agreed by the undertaker and the relevant planning authority.
Annotations
Commencement
- I1
Sch. 10 para. 1 in force at 28.10.2016, see art. 1