Where an application has been made to the relevant planning authority for any agreement or approval required pursuant to a Requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision including the reasons on the application, within a period of 8 weeks beginning with—

(a)

the day immediately following that on which the application is received by the authority; or

(b)

such longer period as may be agreed by the undertaker and the relevant planning authority.