Paragraph 22 Restoration of land used temporarily for constructionI1

England, Wales and Scotland

Any land within the Order limits which is used temporarily for construction is to be reinstated to its former condition, or such condition as the relevant planning authority may approve, within six months of completion of the construction of the authorised development, or such further time as may be approved in writing by the relevant planning authority.