Regulation 13 Building control approval applications for work to existing HRB: validity and time limitI1

England and Wales

(1)

Where the regulator receives a building control approval application for work to existing HRB which is valid the regulator must—

(a)

notify the applicant to that effect, and

(b)

determine it within 8 weeks beginning with the date the application is received by the regulator or within such longer period as at any time the regulator and the applicant agree in writing.

(2)

Where the regulator receives a building control approval application for work to existing HRB which is not valid the regulator must notify the applicant to that effect giving reasons (and where the applicant is not the client, also give a copy of the notification to the client).

(3)

A building control approval application for work to existing HRB is valid if it complies with regulation 12 (building control approval applications for work to existing HRB).

Annotations

Commencement

I1

Reg. 13 in force at 1.10.2023, see reg. 1(1)

Notes on Part 2

Modifications

C1

Pts. 2-6 excluded (temp.) (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 46(2)(c)