OpenLegislation

The Building (Registered Building Control Approvers etc.) (England) Regulations 2024

S.I. 2024/110 · Made 28 January 2024 · Extends to England and Wales

Not fully up to date. 18 changes made by later legislation have not yet been written into this text, which is revised to 1 October 2026.

See the changes not yet applied
ProvisionChangeMade by
Sch. 5 para. 1AinsertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(12)
reg. 8(4)words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(3)
reg. 6(4)words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(2)
Sch. 1 Form 1words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(a)
Sch. 1 Form 2words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(b)
Sch. 1 Form 3words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(c)
reg. 11(4)words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(4)
reg. 13(3)words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(5)
reg. 22A(1)words substitutedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(6)
reg. 25(d)(iva)insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(7)
reg. 37revokedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 12(f)
Sch. 1 Form 4words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(d)
Sch. 1 Form 5words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(e)
Sch. 1 Form 8words insertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(8)(f)
Sch. 2 para. 1AinsertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(9)
Sch. 3 para. 1AinsertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(10)
Sch. 4 para. 1AinsertedBuilding (Local Authority Charges and Amendments Relating to Charging) 2026 reg. 10(11)
reg. 4(2)(xxii)substitutedBuilding Regulations etc. 2026 reg. 4

Building And Buildings, England

Made 28th January 2024

Laid before Parliament 1st February 2024

Coming into force - - 6th April 2024

The Secretary of State makes the following Regulations in exercise of the powers conferred by sections 1(1), 2A, 34, 35(2), 35B(7), 47(1) to (5), 50(1A), (1D), (4), (6), (7) and (7A), 51(1) and (2), 51A(2), (3), (5) and (6), 52(1), (2), (3), (5A) and (7), 52A(1), (2) and (4), 53(2), (4), (4B), (4C) and (7), 53A(6), 53B(5), 53C(3), 53D(2), (3) and (5), 56(1), 58C(5), 58O(4), 58U(4), 58V(4) and 92(2) of, and paragraphs 1, 1A, 1D, 1F, 1G, 1I, 5B, 7, 8 and 10 of Schedule 1 to, the Building Act 1984f1 and sections 25(1) to (3) and (7), 41 and 166(1) of the Building Safety Act 2022f2.

In accordance with section 120B(3) of the Building Act 1984f3 and section 7(4) of the Building Safety Act 2022, the Secretary of State has consulted the building safety regulator and such other persons as the Secretary of State considers appropriate.

Annotations to the whole text

Footnotes

f1

1984 c. 55. Section 1 was amended by section 1 of the Sustainable and Secure Buildings Act 2004 (c.22); section 2A was inserted by section 4 of that Act; section 35 was amended by section 39 of the Building Safety Act 2022 (c. 30) (“the 2022 Act”); section 35B was inserted by section 38 of the 2022 Act. Section 47(1) was amended by section 8 of the Sustainable and Secure Buildings Act 2004 and S.I. 1996/1905; section 50(1A), (1D) and (7A) were inserted by section 49 of the 2022 Act; section 51(1) was substituted, section 51A was inserted and section 52(1) was amended, by S.I. 1996/1905; section 51A was also amended by sections 46(2) and 48(3) of, and paragraph 42 of Schedule 5 to, the 2022 Act; section 52(2) was amended by section 8 of the Sustainable and Secure Buildings Act 2004; section 52(5A) was inserted by section 50(5) of the 2022 Act; section 52A was inserted by section 46 of the 2022 Act; section 53 was amended by sections 36(6) and 52(1) of the 2022 Act; section 53A was inserted by section 36 of the 2022 Act; section 56(1) was amended by S.I. 1996/1905; sections 58C, 58O, 58U and 58V were inserted by section 42 of the 2022 Act. Section 120B was inserted by paragraph 77 of Schedule 5 to the 2022 Act. Paragraphs 1A, 1D, 1F, 1G, 1I and 5B of Schedule 1 were inserted by sections 33 and 34 of the 2022 Act; paragraph 7 of Schedule 1 was amended by section 3 of that Act and by section 11 of the Climate Change and Sustainable Energy Act 2006 (c. 19); paragraph 8 of Schedule 1 was amended by section 3 of the Sustainable and Secure Buildings Act 2004 and by section 40 of the Flood and Water Management Act 2010 (c. 29); paragraph 10 of Schedule 1 was substituted by paragraph 83(8) of Schedule 5 to the 2022 Act. See section 126 for the definition of “prescribed”.

f2

2022 c. 30.

f3

Under the transitional provisions in regulation 5(1) of S.I. 2023/362 the requirement to consult under section 120B of the Building Act 1984 does not apply to proposals consulted on under section 14(3) of the Building Act 1984 before it was repealed by paragraph 17 of Schedule 5 to the Building Safety Act 2022.

Contents

  1. Part 1: General
  2. 1Citation, extent, application and commencement
  3. 2Interpretation
  4. Part 2: Registered building control approvers
  5. 3Independence of approvers
  6. 4Functions of approvers
  7. 5Modifications of 2010 Regulations etc.
  8. Part 3: Notices and certificates etc.
  9. 6Form, grounds and period for rejecting initial notice
  10. 7Invalid notices or certificates
  11. 8Form, grounds and period for rejecting amendment notice
  12. 9Consultation with the fire and rescue authority
  13. 10Consultation with the sewerage undertaker
  14. 11Plans certificate
  15. 12Effect of plans certificate
  16. 13Form, grounds and period for rejecting final certificate
  17. 14Form of notice under section 51C of the 1984 Act
  18. 15Notice before starting work and further notice when work is “commenced” etc.
  19. 15ALevy charging information
  20. 16Lapse of initial notice: commencement of work
  21. 17Notification of dutyholders
  22. 18Compliance declarations
  23. 19Events causing initial notice to cease to be in force
  24. 20Cancellation of initial notices: forms etc.
  25. 21Cancellation of initial notice: notice of contravention of building regulations
  26. Part 4: Transfer of projects back to local authority
  27. 22Local authority powers in relation to partly completed work
  28. 22ACompletion notices
  29. 23Periods within which information on work to which an initial notice relates must be provided
  30. Part 5: Transfer of projects to another approver
  31. 24Section 53(7): prescribed provision
  32. 25Information to be included in transfer certificates
  33. 26Grounds for rejecting a transfer certificate and transfer report
  34. 27Cases where a further initial notice may be given after cancellation of an initial notice under section 53D
  35. Part 6: Appeals under Part 2 of the 1984 Act
  36. 28Appeal under section 50(2) of the 1984 Act
  37. 29Appeals under section 55 of the 1984 Act
  38. Part 7: Registers of notices etc. and registration of approvers
  39. 30Register of notices and certificates
  40. 31Registration periods
  41. 32Notices to local authorities on disciplinary matters in relation to approvers
  42. 33Review of regulator’s decisions under Part 2A of the 1984 Act
  43. 34Appeal in relation to reviewed decisions
  44. Part 8: Miscellaneous
  45. 35Contravention of certain regulations not to be an offence or be subject to a compliance notice
  46. 36Consequential amendments to the Regulatory Reform (Fire Safety) Order 2005 and transitional provision
  47. 37Consequential amendments to the Building (Local Authority Charges) Regulations 2010
  48. 38Amendments to the Building Regulations 2010 and transitional provision
  49. 39Consequential amendment to the Energy Performance of Buildings (England and Wales) Regulations 2012 and transitional provision
  50. 40Consequential amendments to the Building Safety (Registration of Higher-Risk Buildings and Review of Decisions) (England) Regulations 2023
  51. 41Consequential amendments to the Building (Restricted Activities and Functions) (England) Regulations 2023
  52. 42Amendments to the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023
  53. 43Revocations
  54. 44Transitional provisions: approved inspectors who became approvers
  55. 45Transitional provisions: approved inspectors who did not become approvers
  56. 46Transitional provisions: higher-risk building work regarded as sufficiently progressed
  57. 47Transitional provisions: cases where building work supervised by approved inspector is not completed before October 2024
  58. 48Interpretation of Part 8
  59. Signature
  60. Schedule 1Forms
  61. Schedule 2: Grounds for Rejecting an Initial Notice, an Amendment Notice or a Plans Certificate Combined with an Initial Notice
  62. 1Form
  63. 2Wrong local authority
  64. 3Capacity of approver
  65. 4Capacity of approver
  66. 5Breach of section 54B
  67. 6Information about the proposed work
  68. 7Fire and rescue authority
  69. 8Sewerage undertaker
  70. 9Independence
  71. 10Drain connection
  72. 11Local enactments
  73. 12Commencement of work
  74. 13Earlier notice
  75. Schedule 3: Grounds for rejecting a plans certificate or plans certificate combined with an initial notice
  76. 1Form
  77. 2Wrong building control authority
  78. 3Work
  79. 4Optional requirements
  80. 5Plans
  81. 6No initial notice
  82. 7Capacity of approver
  83. 8Breach of section 54B
  84. 9Fire and rescue authority
  85. 10Sewerage undertaker
  86. 11Independence
  87. Schedule 4: Grounds for rejecting a final certificate
  88. 1Form
  89. 2Wrong building control authority
  90. 3Work
  91. 4Optional requirements
  92. 5No initial notice
  93. 6No plans certificate Repealed
  94. 7Capacity of approver
  95. 8Breach of section 54B
  96. 9Lack of fire safety information confirmation
  97. 10Independence
  98. 11Building safety levy
  99. Schedule 5: Grounds for rejecting a transfer certificate and transfer report
  100. 1Required information
  101. 2Wrong local authority
  102. 3No initial notice
  103. 4Capacity of approver
  104. 5Breach of section 54B
  105. 6Earlier notice
  106. 7Local authority action
  107. 8Failure to provide information requested
  108. Explanatory note