OpenLegislation

Regulation 23 Periods within which information on work to which an initial notice relates must be providedI1

England and Wales

(1)

For the purposes of section 53(4B) of the 1984 Act, the period within which a person shown in the initial notice as the registered building control approver (P) is required to give information to the local authority is 21 days beginning with the day on which the local authority gives P a notice under section 53(4A).

(2)

For the purposes of section 53(4C) of the 1984 Act, the period within P is required to give information to the person carrying out or intending to carry out the work (C) is—

(a)

21 days beginning with the day on which the local authority gave P a notice under section 53(4A), or

(b)

in relation to information requested by C pursuant to section 53(4C)(c), 21 days beginning with the date on which C gives P a notice under section 53(4C)(c).

Annotations

Commencement

I1

Reg. 23 in force at 6.4.2024, see reg. 1(3)