Regulation 13 Form, grounds and period for rejecting final certificateI1
England and Wales
The prescribed form of a final certificatef1 is form 5 in Schedule 1.
The grounds on which a local authority must reject a final certificate are those prescribed in Schedule 4 and the form to be used for rejecting a final certificate is form 7 in Schedule 1.
The period within which a local authority may give notice of rejection of a final certificate is ten working days beginning with the day on which the certificate is given.
A final certificate given by an approver to a local authority in accordance with these Regulations is evidence (but not conclusive evidence) that the requirements specified in the certificate have been complied with.
Annotations
Commencement
Footnotes
- f1
-
For the definition of “final certificate” see section 51 of the Building Act 1984.