Regulation 28 Form, grounds and period for rejecting public body’s plans certificateI1
England and Wales
The prescribed form of a public body’s plans certificate—
which is not combined with a public body’s notice, is Form PB2(W) in Schedule 1, or
which is combined with a public body’s notice, is Form PB3(W) in Schedule 1.
The grounds on which a local authority must reject a public body’s plans certificate are those prescribed in Schedule 7.
The grounds on which a local authority must reject a public body’s plans certificate combined with a public body’s notice are those prescribed in Schedule 6 and Schedule 7.
The period within which a local authority may give notice of rejection of a public body’s plans certificate or combined notice and certificate is 10 working days beginning on the day on which the certificate is given.