Regulation 11 Transitional provision: new higher-risk building work
England and Wales
Any new higher-risk building work must be overseen by the F1building control authority on or after 6 April 2024.
Initial notices for higher-risk building work must not be submitted to a local authority by an approved inspector or a registered building control authority on or after 6 April 2024.
For the purposes of paragraph (1), new higher-risk building work means higher-risk building work which is not already detailed in an initial notice F2only relating to building work submitted and accepted, or deemed to be accepted, before 6 April 2024.
In paragraph (1), “building control authority” means the local authority as stated in section 121A of the Building Act 1984.
Annotations
Textual amendments
- F1
Words in reg. 11(1) substituted (1.7.2026) by The Building Safety Act 2022 (Consequential Amendments) (Wales) Regulations 2026 (W.S.I. 2026/55), regs. 1(2), 11(2)(a) (with reg. 13)
- F2
Words in reg. 11(3) inserted (1.1.2025) by The Building (Registered Building Control Approvers etc.) (Wales) Regulations 2024 (S.I. 2024/1268), regs. 1(2), 42(4)
- F3
Reg. 11(4) inserted (1.7.2026) by The Building Safety Act 2022 (Consequential Amendments) (Wales) Regulations 2026 (W.S.I. 2026/55), regs. 1(2), 11(2)(b) (with reg. 13)