OpenLegislation

Paragraph 6.7 Commissioning building servicesF1

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

Every building must be designed and constructed in such a way that energy supply systems F2, control systems and building services which use fuel or power for heating, lighting, ventilating and cooling the internal environment and heating the water, are commissioned to achieve F3effective operation and optimum energy efficiency.

Limitation

This standard does not apply to–

(a)

major power plants serving the National Grid;

(b)

the process and emergency lighting components of a building;

(c)

heating provided solely for the purpose of frost protection; or

(d)

energy supply systems used solely for industrial and commercial processes, leisure use and emergency use within a building.

Annotations

Textual amendments

F1

Schs. 1-6 substituted (1.5.2007) by The Building (Scotland) Amendment Regulations 2006 (S.S.I. 2006/534), regs. 1, 2(c), sch. (with regs. 3, 4)

F2

Words in sch. 5 para. 6.7 inserted (1.2.2023) by The Building (Scotland) Amendment Regulations 2022 (S.S.I. 2022/136), regs. 1(3), 9(c)(i) (with reg. 11) (as amended by S.S.I. 2022/340, reg. 2)