Paragraph 43 ArbitrationI1
England and Wales
Save for differences or disputes arising under paragraphs 34(2), 34(4) and 37 any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 40 (arbitration).
Annotations
Commencement
- I1
Sch. 11 para. 43 in force at 14.8.2025, see art. 1