The Byers Gill Solar Order 2025
S.I. 2025/934 · Made 23 July 2025 · Extends to England and Wales
Infrastructure Planning
Made 23rd July 2025
Coming into force 14th August 2025
The application has been examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The Examining Authority, having considered the representations made and not withdrawn and the application together with the accompanying documents, has, in accordance with section 74(2) of the 2008 Act, submitted a report and recommendation to the Secretary of State.
The Secretary of State has considered the representations made and not withdrawn, and the recommendation and report of the Examining Authority, and taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4 and has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.
The Secretary of State is satisfied that the special category land within the Order limits, when burdened with the rights imposed by this Order, will be no less advantageous than it was before to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and to the public; and that, accordingly, section 132(3) of the 2008 Act applies.
The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application on the terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120, 122, 123 and 140 of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f2
-
S.I. 2009/2264, amended by S.I. 2010/602, S.I. 2010/602, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2015/377, S.I. 2017/572; modified by S.I. 2012/1659.
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
- f4
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc. granted by the Order
- 4Maintenance of authorised development
- 5Operation of generating stations
- 6Consent to transfer benefit of Order
- 7Disapplication and modification of legislative provisions
- 8Defence to proceedings in respect of statutory nuisance
- Part 3: STREETS
- 9Street works
- 10Application of the 1991 Act
- 11Power to alter layout, etc., of streets
- 12Construction and maintenance of altered streets
- 13Temporary closure of public rights of way
- 14Public rights of way
- 15Access to works
- 16Agreements with street authorities
- 17Traffic regulation measures
- Part 4: SUPPLEMENTAL POWERS
- 18Discharge of water
- 19Protective work to buildings
- 20Authority to survey and investigate the land
- Part 5: POWERS OF ACQUISITION
- 21Compulsory acquisition of land
- 22Time limit for exercise of authority to acquire land compulsorily
- 23Compulsory acquisition of rights
- 24Private rights
- 25Acquisition of subsoil only
- 26Application of the 1981 Act
- 27Power to override easements and other rights
- 28Modification of Part 1 of the Compulsory Purchase Act 1965
- 29Rights under or over streets
- 30Temporary use of land for carrying out the authorised development
- 31Temporary use of land for maintaining authorised development
- 32Statutory undertakers
- 33Apparatus and rights of statutory undertakers in temporarily closed streets
- 34Recovery of costs of new connections
- Part 6: GENERAL
- 35Operational land for the purposes of the 1990 Act
- 36Certification of plans, etc.
- 37Service of notices
- 38Felling or lopping of trees or removal of hedgerows
- 39Trees subject to tree preservation orders
- 40Arbitration
- 41Requirements, appeals, etc.
- 42Application of landlord and tenant law
- 43Crown rights
- 44Protective provisions
- 45Funding
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- Schedule 2: REQUIREMENTS
- Part 1: REQUIREMENTS
- 1Time limits
- 2Phases of authorised development and date of final commissioning
- 3Detailed design approval
- 4Construction environmental management plans (CEMP)
- 5Decommissioning and restoration
- 6Construction traffic management plan (CTMP)
- 7Pollution and Spillage
- 8Materials Management
- 9Site Waste
- 10Soil Management
- 11Battery safety management
- 12Landscape and ecological management plan (LEMP)
- 13Implementation and maintenance of landscaping
- 14Public rights of way diversions
- 15Construction hours
- 16Construction noise
- 17Fencing and other means of enclosure
- 18Archaeology
- 19Surface and foul water drainage
- 20Requirement for written approval
- 21Amendments to approved details
- 22Consultation
- Part 2: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- 23Interpretation
- 24Applications made under requirements
- 25Further information regarding requirements
- 26Appeals
- 27Fees
- Schedule 3: STREETS SUBJECT TO STREET WORKS
- 1Interpretation
- Schedule 4: ALTERATION OF STREETS
- 1PERMANENT ALTERATION OF LAYOUT AND MAINTAINED BY THE HIGHWAY AUTHORITY
- 2TEMPORARY ALTERATION OF LAYOUT
- Schedule 5: PUBLIC RIGHTS OF WAY TO BE CLOSED
- 1PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED
- 2Public rights of way to be permanently stopped up
- Schedule 6: ACCESS TO WORKS
- 1PERMANENT MEANS OF ACCESS TO WORKS
- 2TEMPORARY MEANS OF ACCESS TO WORKS
- Schedule 7REMOVAL OF HEDGEROWS
- Schedule 8LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- Schedule 9: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR THE CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICITVE COVENANTS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Application of Part 1 of the 1965 Act
- 5Application of Part 1 of the 1965 Act
- 6Application of Part 1 of the 1965 Act
- 7Application of Part 1 of the 1965 Act
- 8Application of Part 1 of the 1965 Act
- 9Application of Part 1 of the 1965 Act
- 10Application of Part 1 of the 1965 Act
- 11Application of Part 1 of the 1965 Act
- Schedule 10LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 11: PROTECTIVE PROVISIONS
- Part 1: PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Application
- 2Application
- 3Precedence of the 1991 Act in respect of apparatus in the streets
- 4No acquisition etc. except by agreement
- 5Removal of apparatus
- 6Facilities and rights for alternative apparatus
- 7Retained apparatus
- 8Expenses and costs
- 9Expenses and costs
- 10Enactments and agreements
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- Part 3: FOR THE PROTECTION OF THE DRAINAGE AUTHORITIES
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Paragraph 23
- 24Paragraph 24
- 25Paragraph 25
- 26Paragraph 26
- 27Paragraph 27
- Part 4: FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY TRANSMISSION PLC AS ELECTRICITY UNDERTAKER
- 28Application
- 29Interpretation
- 30Interaction with the EGL1 Project
- 31On Street Apparatus
- 32Apparatus of National Grid Electricity Transmission Plc in stopped up and temporarily closed streets
- 33Protective works to buildings
- 34Acquisition of land
- 35Removal of apparatus
- 36Facilities and rights for alternative apparatus
- 37Retained apparatus: protection of National Grid Electricity Transmission Plc as Electricity Undertaker
- 38Expenses
- 39Indemnity
- 40Enactments and agreements
- 41Co-operation
- 42Access
- 43Arbitration
- 44Notices
- Part 5: FOR THE PROTECTION OF NATIONAL GAS TRANSMISSION PLC AS GAS UNDERTAKER
- 45Application
- 46Interpretation
- 47On Street Apparatus
- 48Apparatus of National Gas in stopped up and temporarily closed streets
- 49Protective works to buildings
- 50Acquisition of land
- 51Removal of apparatus
- 52Facilities and rights for alternative apparatus
- 53Retained apparatus: protection
- 54Expenses
- 55Indemnity
- 56Enactments and agreements
- 57Co-operation
- 58Access
- 59Arbitration
- 60Notices
- Part 6: FOR THE PROTECTION OF NORTHERN POWERGRID
- 61Paragraph 61
- 62Paragraph 62
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- 68Paragraph 68
- 69Paragraph 69
- 70Paragraph 70
- 71Paragraph 71
- 72Paragraph 72
- 73Paragraph 73
- 74Paragraph 74
- 75Paragraph 75
- 76Paragraph 76
- 77Paragraph 77
- 78Paragraph 78
- Part 7: FOR THE PROTECTION OF NORTHUMBRIAN WATER LIMITED
- 79Paragraph 79
- 80Paragraph 80
- 81On street apparatus
- 82Compulsory acquisition
- 83Protection Strips
- 84Alteration of NWL Apparatus
- 85Access
- 86Protective Works to Buildings
- 87Removal of Apparatus
- 88Facilities and rights for alternative apparatus
- 89Apparatus in stopped up and temporarily closed streets
- 90Unmapped sewers/other apparatus
- 91Expenses and costs
- 92Indemnity
- 93Arbitration
- 94Duty to cooperate
- 95Enactments and agreements
- Part 8: FOR THE PROTECTION OF NORTHERN GAS NETWORK’S APPARATUS
- 96Application
- 97Interpretation
- 98Interpretation
- 99Apparatus of Statutory undertaker in stopped up and temporarily closed streets
- 100Acquisition of land
- 101Removal or diversion of apparatus
- 102Facilities and rights for alternative apparatus
- 103Retained apparatus: protection
- 104Expenses
- 105Indemnity
- 106Enactments and agreements
- 107Co-operation
- 108Access
- 109Arbitration
- 110Works falling outside of development authorised by the Order
- 111Cathodic protection testing
- Schedule 12: ARBITRATION RULES
- 1Primary objective
- 2Time periods
- 3Timetable
- 4Procedure
- 5Arbitrator’s powers
- 6Costs
- 7Confidentiality
- Schedule 13DOCUMENTS TO BE CERTIFIED
- Explanatory note