Paragraph 3 Detailed design approvalI1
England and Wales
No phase of the authorised development may commence until details of—
the layout;
scale;
proposed finished ground levels;
external appearance;
hard surfacing materials;
vehicular and pedestrian access, parking and circulation areas;
refuse or other storage units, signs and lighting;
drainage, water, power and communications cables and pipelines;
programme for landscaping works;
security measures;
fencing; and
any mitigation measures necessary to address noise impacts
relating to that phase have been submitted to and approved in writing by the relevant planning authority.
The details submitted must accord with—
the location plan and order limits;
the works plans;
the environmental masterplan;
the outline LEMP;
the principles and assessments set out in the environmental statement; and
the design approach document, or such variation thereof as may be approved by the relevant planning authority pursuant to requirement 19.
The authorised development must be carried out in accordance with the approved details.