Paragraph 19 Surface and foul water drainageI1
England and Wales
No phase of the authorised development is to be commenced until written details of the surface and foul water drainage scheme for that phase have been submitted to and approved by the local planning authority in consultation with the Environment Agency.
The details submitted under sub-paragraph (1) must include:
the plans and strategies referred to in Appendix 10.1 flood risk assessment and drainage strategy of the environmental statement (document reference 6.4.10.1 Revision 6); and
details of how flood risk will be managed during construction and operation in areas of increased flood risk, with reference to the Environment Agency’s latest Flood Map for Planning.
The surface and foul water drainage system for the relevant part of the authorised development must be constructed in accordance with the approved details.
For the purposes of paragraph (1), “commence” includes any site preparation works.
Annotations
Commencement
- I1
Sch. 2 para. 19 in force at 14.8.2025, see art. 1