Paragraph 94 Duty to cooperateI1
England and Wales
Where in consequence of the proposed construction of any of the authorised development, the undertaker or NWL requires the removal of apparatus or NWL makes requirements for the protection or alteration of apparatus, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of NWL’s undertaking and NWL must use all reasonable endeavours to co-operate with the undertaker for that purpose.