OpenLegislation

Article 3 Development consent etc granted by the OrderI1

England and Wales

(1)

Subject to the provisions of this Order, and to the Requirements in Part 3 of Schedule 1, the undertaker is granted—

(a)

development consent for the authorised development in Part 1 of Schedule 1, and

(b)

consent for the ancillary works in Part 2 of Schedule 1,

to be carried out within the Order limits.

(2)

Subject to article 6 (power to deviate), the authorised development may only be constructed in the lines or situations shown on the works plan.

(3)

Notwithstanding anything in this Order or shown on the works plan but without prejudice to the provisions of article 6 (power to deviate) the undertaker may construct—

(a)

Works No. 2A, 5A and 14A or Works No. 2B, 5B and 14B but may not construct both Works No. 2A, 5A and 14A and Works No. 2B, 5B and 14B under the powers conferred by this Order, and

(b)

Work No. 4A or 4B but may not construct more than one of those works under the powers conferred by this Order.

(4)

Where the undertaker constructs—

(a)

either Work No. 4A or Work No. 4B as part of the authorised development, the undertaker must notify the relevant planning authority prior to the commencement of the authorised development which of those Works it intends to construct, and

(b)

either Works No. 5A and 14A or Works No. 5B and 14B as part of the authorised development, the undertaker must notify the relevant planning authority prior to the commencement of the authorised development which of those Works it intends to construct.

Annotations

Commencement

I1

Art. 3 in force at 2.10.2014, see art. 1