The Clocaenog Forest Wind Farm Order 2014
S.I. 2014/2441 · Made 11 September 2014 · Extends to England and Wales
Infrastructure Planning
Made 11th September 2014
Coming into force 2nd October 2014
The application was examined by a single appointed person appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The single appointed person, having examined the application with the documents that accompanied the application, and the representations made and not withdrawn, has, in accordance with section 83(1) and (2) of the 2008 Act, made a report and recommendation to the Secretary of State.
The Secretary of State, having considered the report and recommendation of the single appointed person, and decided the application, has determined to make an Order giving effect to the proposals comprised in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, and 120 of the 2008 Act, makes the following Order:
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264. Amended by S.I. 2010/602, 2012/635, 2012/2732.
- f2
-
2008 c.29. The relevant provisions of the Planning Act 2008 are amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c.20), and by sections 22 to 27 of the Growth and Infrastructure Act 2013 (c.27). There are other amendments to the 2008 Act which are not relevant to this Order.
- f3
-
S.I. 2010/103. Amended by SI 2012/635.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- Part 2: Principal powers
- 3Development consent etc granted by the Order
- 4Procedure in relation to approvals etc under Requirements
- 5Maintenance of authorised project
- 6Power to deviate
- 7Operation of generating station
- 8Benefit of Order
- 9Defence to proceedings in respect of statutory nuisance
- 10Street works
- 11Stopping up of streets
- 12Public rights of way
- 13Application of the 1991 Act
- 14Temporary stopping up of streets
- 15Access to works
- 16Construction and maintenance of new or altered streets
- 17Agreements with street authorities
- 18Discharge of water
- 19Authority to survey and investigate the land
- Part 3: Powers of acquisition
- 20Compulsory acquisition of land and rights
- 21Time limit for exercise of authority to acquire land compulsorily
- 22Application and modification of legislative provisions
- 23Compulsory acquisition of rights
- 24Private rights
- 25Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- Part 4: Miscellaneous and general
- 26Application of landlord and tenant law
- 27Operational land for purposes of the 1990 Act
- 28Felling or lopping of trees
- 29Statutory undertakers
- 30Apparatus and rights of statutory undertakers in stopped-up streets
- 31Recovery of costs of new connections
- 32Removal of human remains
- 33Crown rights
- 34Service of notices
- 35Protection of interests
- 36Certification of plans etc
- 37Arbitration
- Signature
- Schedule 1: Authorised project
- 1Authorised development
- Part 2: Ancillary works
- 1Highway works
- Part 3: Requirements
- 1Definitions
- 2Submission and approval of details
- 3Time limits
- 4Expiry of development consent
- 5Decommissioning and site restoration
- 6Failure of turbines
- 7Plans
- 8Construction traffic management plan
- 9Construction method statement
- 10Highways
- 11Paragraph 11
- 12Paragraph 12
- 13Construction hours
- 14Paragraph 14
- 15Habitat management plan
- 16Access management plan
- 17Felling
- 18Appearance
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Shadow flicker
- 24Archaeology
- 25Ecological clerk of works
- 26Surface water drainage
- 27Accumulation and deposits
- 28Infra-red aviation lighting
- 29Defence Geographic Centre
- 30Noise
- 31Paragraph 31
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- Part 4: Noise Guidance for Requirements 30 to 35
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- Schedule 2Streets subject to street works
- Schedule 3Streets to be stopped up
- Schedule 4Streets to be temporarily stopped up
- Schedule 5Access to works
- Schedule 6: Land subject to acquisition of new rights and interference with private rights
- 1Land subject to acquisition of new rights
- 2Land subject to interference with private rights
- Schedule 7: Modification of compensation and compulsory purchase enactments for creation of new rights
- 1Compensation enactments
- 2Paragraph 2
- 3Application of the 1965 Act
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- Schedule 8: Protection for electricity, gas, water and sewerage undertakers
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- Explanatory note