Paragraph 18 AppearanceI1
England and Wales
The wind turbines may not be erected until details of their external appearance and colour and surface finish and the design and appearance of the associated external transformer/switchgear units (if any) have been submitted to and approved by the relevant planning authority. The authorised development must be completed in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 18 in force at 2.10.2014, see art. 1