Paragraph 24 ArchaeologyI1
England and Wales
No authorised development may commence until a scheme of archaeological investigation has been submitted to and approved by the relevant planning authority.
The scheme of archaeological investigation must incorporate—
a walkover survey before commencement of the authorised development;
fencing to be provided around Twr yr Hill round barrow and Maen Cred standing stone during construction works;
where presence of archaeological remains is established a watching brief will be undertaken during construction to record the surviving archaeological remains;
a watching brief during construction of all other infrastructure to record any previously unknown archaeological remains that may be present; and
proposed peat core sampling.
The scheme of archaeological investigation shall be implemented as approved.