Paragraph 23 Shadow flickerI1
England and Wales
The authorised development may not commence until a scheme for the avoidance of any shadow flicker effect at any dwelling which lawfully existed or had planning permission at the date of this Order has been submitted to and approved by the relevant planning authority. The scheme must include a time limit for the investigation of complaints, and for the implementation of mitigation measures. The scheme is to be implemented as approved.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 23 in force at 2.10.2014, see art. 1