Paragraph 10 HighwaysI1
England and Wales
No wind turbine parts may be delivered to the site before detailed plans and drawings in respect of Work No. 4A or 4B (whichever is decided on by the undertaker) have been submitted to and approved by the relevant planning authority and such works have been constructed in accordance with the plans and drawings so approved.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 10 in force at 2.10.2014, see art. 1