OpenLegislation

Paragraph 27 Accumulation and depositsI1

England and Wales

(1)

No authorised development may commence until, following consultation with NRW, a written scheme for the management of any accumulations and deposits has been submitted to and approved by the relevant planning authority.

(2)

The approved scheme for the management of accumulations and deposits is to be implemented before and maintained during the construction, operation and decommissioning of the authorised development.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 27 in force at 2.10.2014, see art. 1