The Community Infrastructure Levy Regulations 2010
S.I. 2010/948 · Made 23 March 2010 · Extends to England and Wales
Community Infrastructure Levy, England And Wales
Made 23rd March 2010
Coming into force 6th April 2010
Accordingly, the Secretary of State in exercise of the powers conferred by sections 205(1) and (2), 208(2)(b), (4), (5), (7) and (8), 209(2)(a), (3) to (6) and (8), 210(1) to (3) and (5), 211(2) and (3) to (7), 212(9) and (10), 213(4), 214(2), 215(1) to (3), 216(1), (3), (4), (6) and (7), 217(1) to (7), 218(1) to (3), (4)(a) and (b), (4)(d) to (k) and (5) to (11), 220(1), (2)(a) to (s) and (3)(a) to (c), 222(1) and 223(1)(a), (2) and (4) of the Planning Act 2008, and with the consent of the Treasury, makes the following Regulations:C5
Annotations to the whole text
Modifications
- C1
Regulations applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 11 (with arts. 48, 68, 79)
- C2
Regulations applied (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 9 (with art. 32)
- C3
Regulations applied (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 9(1) (with art. 22)
- C4
Regulations applied (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 10(2) (with art. 37)
- C5
Regulations continued (temp.) (25.3.2026) by The Levelling-up and Regeneration Act 2023 (Commencement No. 11 and Saving and Transitional Provisions) Regulations 2026 (S.I. 2026/169), reg. 1(3), Sch. 1
Footnotes
- f1
Contents
- Part 1: INTRODUCTORY
- 1Citation and commencement
- 2Interpretation
- 3Community Infrastructure Levy
- Part 2: DEFINITION OF KEY TERMS
- 4Meaning of “owner” and “material interest”
- 5Meaning of “planning permission”
- 6Meaning of “development”
- 7Commencement of development
- 8Time at which planning permission first permits development
- 9Meaning of “chargeable development”
- 10Meaning of “collecting authority”
- Part 3: CHARGING SCHEDULES
- 11Interpretation and application of Part 3
- 11AExercise of Part 3 functions in anticipation that an MDC will be established
- 12Format and content of charging schedules
- 13Differential rates
- 14Setting rates
- 15Consultation on a preliminary draft charging schedule
- 16Publication of a draft charging schedule
- 17Representations relating to a draft charging schedule
- 18Withdrawal of a draft charging schedule
- 19Submission of documents and information to the examiner
- 20Consideration of representations by examiner
- 21CIL examination: right to be heard
- 22Joint examinations
- 23Publication of the examiner’s recommendations
- 24Correction of errors in examiner’s recommendations
- 25Approval and publication of a charging schedule
- 26Correction of errors in a charging schedule
- 27Effect of correction of a charging schedule
- 28Charging schedule: effect
- 28ACharging schedules: procedure in relation to a charging schedule ceasing to have effect
- 29Payment of fees and expenses of independent persons
- 30Recovery of costs incurred by the Secretary of State
- Part 4: LIABILITY
- 31Assumption of liability
- 32Transfer of assumed liability
- 33Default liability
- 34Apportionment of liability
- 35Apportionment of liability: information notice
- 36Default of liability
- 37Joint liability
- 38Interests held on trust
- 39Effect of death on assumed liability
- Part 5: CHARGEABLE AMOUNT
- 40Calculation of chargeable amount
- Part 6: EXEMPTIONS AND RELIEF
- 41Interpretation of Part 6
- 42Exemption for minor development
- 42AExemption for residential annexes or extensions
- 42BExemption for residential annexes or extensions: procedure
- 42CWithdrawal of the exemption for residential annexes
- 43Exemption for charities
- 44Discretionary charitable relief: investment activities
- 45Other discretionary charitable relief Repealed
- 46Discretionary charitable relief: notification requirements
- 47Charitable relief: procedure
- 48Withdrawal of charitable relief
- 49Social housing relief
- 49ADiscretionary social housing relief
- 49BDiscretionary social housing relief: notification requirements
- 49CSocial housing relief: qualifying communal development
- 50Social housing relief: qualifying amount
- 51Social housing relief: procedure
- 52Social housing relief: disposal of land before occupation
- 53Withdrawal of social housing relief
- 54Social housing relief: information notice
- 54AExemption for self-build housing
- 54BExemption for self-build housing: procedure
- 54CExemption for self-build housing: completion of development
- 54DWithdrawal of the exemption for self-build housing
- 55Discretionary relief for exceptional circumstances
- 56Exceptional circumstances: notification requirements
- 57Exceptional circumstances: procedure
- 58Exceptional circumstances: procedure in London
- 58ZACarry over of relief in relation to certain section 73 permissions
- Part 7: APPLICATION OF CIL
- 58AInterpretation of Part 7
- 59Application to infrastructure
- 59ADuty to pass CIL to local councils
- 59BApplication of regulation 59A to land and infrastructure payments
- 59CApplication of CIL by local councils
- 59DPayment periods
- 59ERecovery of CIL passed in accordance with regulation 59A or 59B
- 59FUse of CIL in an area to which regulations 59A and 59B do not apply
- 60Reimbursement of expenditure incurred and repayment of loans
- 61Administrative expenses
- 62Reporting
- 62AReporting by local councils
- 63Infrastructure: amendment to section 216 of the Planning Act 2008
- Part 8: ADMINISTRATION
- 63ATransitional provision: when a MDC becomes the charging authority for an area
- 63BTransitional provision: when a MDC ceases being the charging authority for an area
- 64Notice of chargeable development
- 64APreparation and service of notice of chargeable development by collecting authority
- 65Liability notice
- 66Local land charges
- 67Commencement notice
- 68Deemed commencement of chargeable development
- 69Demand notice
- 69ASuspension of demand notice
- 69BInstalment policies
- 70Payment periods
- 71Payment in full
- 72Payment: general
- 72APayment: deferral
- 72BDeferral: payment of surcharge and interest
- 72CDeferral: information
- 73Payment in kind
- 73AInfrastructure payments
- 73BInfrastructure payments: notification requirements
- 74Payment in kind and infrastructure payments: further provision
- 74AAbatement : section 73 applications
- 74BAbatement: implementation of a different planning permission
- 75Overpayment
- 76Payments to charging authorities
- 77Duty to supply information to collecting authority
- 78Requests for information by collecting authority
- 79Use of information by collecting authority
- Part 9: ENFORCEMENT
- Chapter 1: SURCHARGES AND INTEREST
- 80Surcharge for failure to assume liability
- 81Surcharge: apportionment of liability
- 82Surcharge for failure to submit a notice of chargeable development
- 83Surcharge for failure to submit a commencement notice
- 84Surcharge: disqualifying events
- 85Surcharge for late payment
- 86Surcharge for failure to comply with an information notice
- 87Late payment interest
- 88Surcharges and interest: general
- Chapter 2: CIL STOP NOTICES
- 89Preliminary steps
- 90Service of CIL stop notice
- 91Withdrawal of a CIL stop notice
- 92Registration of a CIL stop notice
- 93Offence
- 94Injunctions
- Chapter 3: RECOVERY OF CIL
- 95Interpretation and application of Chapter 3
- 96Liability orders: reminder notice
- 97Application for liability order
- 98Enforcement by taking control of goods
- 99Appeals in connection with distress
- 100Commitment to prison
- 101Commitment to prison: further provision
- 102Magistrates’ courts
- 103Charging orders
- 104Charging orders: further provision
- 105Insolvency
- 106Recovery in a court of competent jurisdiction
- 107Enforcement of local land charges
- Chapter 4: OTHER ENFORCEMENT PROVISIONS
- 108Outstanding liabilities on death
- 108APower to require information
- 109Powers of entry
- 110Offence for supplying false information
- 111Prosecution of CIL offences
- Part 10: APPEALS
- 112Interpretation of Part 10
- 113Review of chargeable amount
- 114Chargeable amount: appeal
- 115Apportionment of liability: appeal
- 116Charitable relief: appeal
- 116AExemption for residential annexes: appeal
- 116BExemption for self-build housing: appeal
- 117Surcharge: appeal
- 118Deemed commencement
- 119CIL stop notices
- 120Appeal procedure
- 121Costs
- Part 10A: Reporting and monitoring on CIL and planning obligations
- 121AAnnual infrastructure funding statements
- 121BReporting by parish councils
- 121CAnnual CIL rate summary
- Part 11: PLANNING OBLIGATIONS
- 122Limitation on use of planning obligations
- 123Further limitations on use of planning obligations
- Part 12: MISCELLANEOUS AND TRANSITIONAL PROVISIONS
- 124Payment of CIL by the Crown
- 125Enforcement in relation to the Crown and Parliament
- 126Service of documents: general
- 127Service of documents on the Crown and Parliament
- 128Transitional provision: general
- 128ATransitional provision: section 73 of TCPA 1990 applications
- 128BTransitional provision: article 18(1) of DMPO applications
- 129Transitional provision: charging schedule ceases to have effect
- Signature
- Schedule 1: Calculation of chargeable amount etc
- Part 1: Standard cases
- 1Chargeable amount: standard cases
- 2Chargeable amount: outline permissions where first permits date is after new charging schedule
- Part 2: ‘Amended’ planning permissions
- 3Chargeable amount etc: ‘amended’ planning permissions
- 4Amount of CIL payable: section 73 permissions which increase liability
- 5Amount of CIL payable: section 73 permissions which reduce liability
- Part 3: Calculation of social housing relief
- 6Social housing relief: calculating qualifying amount
- Part 4: Pre-CIL permissions ‘amended’ when CIL is in effect
- 7Amount of CIL payable: pre-CIL permissions ‘amended’ when CIL is in effect
- 8Transitional cases: pre-CIL phased permissions ‘amended’ when CIL is in effect
- Part 5: Pre-CIL permissions ‘amended’ when CIL in effect: appeal
- 9Pre-CIL permissions ‘amended’ when CIL in effect: appeal in relation to notional relief
- Schedule 2: Matters to be included in the annual infrastructure funding statement
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- Explanatory note