Paragraph 3 I1
England, Wales and Scotland
In respect of the relevant CFD unit—
where the unit is an offshore wind CFD unit, whether or not it is to be constructed in phases and, if it is,—
the amount of electricity to be generated by each phase; and
the target dates for completion of each phase of construction;
the type of eligible generating station; and
which reference price (as defined in the F3contract allocation framework) applies to the CFD unit.
Annotations
Textual amendments
- F1
Sch. 1 para. 3(a)(iv) substituted (20.7.2016) by The Contracts for Difference (Miscellaneous Amendments) Regulations 2016 (S.I. 2016/784), regs. 1(1), 19(d)
- F2
Sch. 1 para. 3(a)(v) omitted (25.6.2021) by virtue of The Contracts for Difference (Miscellaneous Amendments) Regulations 2021 (S.I. 2021/758), regs. 1(1), 25
- F3
Words in Sch. 1 para. 3(d) substituted (13.6.2024) by The Contracts for Difference (Sustainable Industry Rewards) Regulations 2024 (S.I. 2024/710), regs. 1(1), 51(a)
Commencement
- I1
Sch. 1 para. 3 in force at 1.8.2014, see reg. 1(1)